8409-8411 N CHIMINEAS AVE 91325
Certificate Information: 8409-8411 N CHIMINEAS AVE 91325
- Application / Permit
- 22014-30000-00567
- Plan Check / Job No.
- B22WL00528
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE OF 1 STORY SFD TO ADU & ADD A 2ND STORY ABOVE THE ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 2/9/2022 | APPLICANT |
Assigned to Plan Check Engineer | 2/24/2022 | KAVIAN REFAHI |
Corrections Issued | 2/28/2022 | KAVIAN REFAHI |
Quality Review Completed | 3/11/2022 | FELIX FIGUEROA |
Building Plans Picked Up | 3/14/2022 | APPLICANT |
Applicant returned to address corrections | 3/22/2022 | KAVIAN REFAHI |
Applicant returned to address corrections | 4/6/2022 | KAVIAN REFAHI |
Plan Check Approved | 4/26/2022 | KAVIAN REFAHI |
Issued | 9/19/2022 | APPLICANT |
CofO in Progress | 4/10/2023 | JUSTIN HAWLEY |
Permit Finaled | 5/4/2023 | JOHN JANSON |
CofO Issued | 5/4/2023 | JOHN JANSON |
Permit Finaled | 5/4/2023 | JOHN JANSON |
Permit Application Clearance Information
Address approval | Cleared | 3/4/2022 | JOSE DUARTE-DIAZ |
Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | JOSE DUARTE-DIAZ |
Roof/Waste drainage to street | Cleared | 3/4/2022 | JOSE DUARTE-DIAZ |
Sewer availability | Cleared | 3/4/2022 | JOSE DUARTE-DIAZ |
Contact Information
Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
Contractor | Owner-Builder | , |
Inspector Information
DAVID SCANTLIN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
KRISTEN BEVERIDGE, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Drilled-In Anchors | 12/9/2022 | Approved | SEAN HAUPT |
Footing/Foundation/Slab | 12/19/2022 | Corrections Issued | SEAN HAUPT |
Footing/Foundation/Slab | 12/28/2022 | Corrections Issued | SEAN HAUPT |
Footing/Foundation/Slab | 1/6/2023 | Approved | JOHN KIDWELL |
Deputy Wood Construction | 1/12/2023 | Partial Approval | JOHN KIDWELL |
BUILDING-Rough-Frame | 1/13/2023 | Corrections Issued | JOHN KIDWELL |
Green Building Rough | 1/13/2023 | Not Ready for Inspection | JOHN KIDWELL |
Interior/Exterior Lathing | 2/6/2023 | Partial Approval | DAVID SCANTLIN |
BUILDING-Rough-Frame | 2/9/2023 | Not Ready for Inspection | MORRIS JACKSON |
Green Building Rough | 2/9/2023 | Not Ready for Inspection | MORRIS JACKSON |
HVAC-Rough | 2/9/2023 | Corrections Issued | MORRIS JACKSON |
Special/Order Compliance | 2/9/2023 | Approved | DAVID SCANTLIN |
BUILDING-Rough-Frame | 2/13/2023 | Approved | DAVID SCANTLIN |
Green Building Rough | 2/13/2023 | Approved | DAVID SCANTLIN |
HVAC-Rough | 2/13/2023 | Approved | DAVID SCANTLIN |
PLUMBING-Rough | 2/13/2023 | Approved | DAVID SCANTLIN |
Shower Pan | 2/13/2023 | Approved | DAVID SCANTLIN |
Insulation | 2/14/2023 | Approved | DAVID SCANTLIN |
Drywall Nailing | 2/17/2023 | Partial Approval | JON MCHUGH |
ELECTRICAL-Rough | 2/17/2023 | Corrections Issued | JON MCHUGH |
BUILDING-Rough-Frame | 3/1/2023 | Corrections Issued | DAVID SANDOVAL |
Interior/Exterior Lathing | 3/1/2023 | Approved | DAVID SANDOVAL |
Special/Order Compliance | 3/1/2023 | Partial Inspection | JUSTIN HAWLEY |
Special/Order Compliance | 3/3/2023 | Approved | DAVID SCANTLIN |
Pre-Inspection | 3/14/2023 | Approved | JEFFREY BULL |
Special/Order Compliance | 3/14/2023 | Partial Inspection | JUSTIN HAWLEY |
Final | 4/3/2023 | Corrections Issued | DAVID SCANTLIN |
BUILDING-Rough-Frame | 4/10/2023 | Approved | JUSTIN HAWLEY |
ELECTRICAL-Final | 4/10/2023 | Approved | JUSTIN HAWLEY |
Final | 4/10/2023 | OK to Issue CofO | JUSTIN HAWLEY |
Green Building Final | 4/10/2023 | Approved | JUSTIN HAWLEY |
HVAC-Final | 4/10/2023 | Approved | JUSTIN HAWLEY |
PLUMBING-Final | 4/10/2023 | Approved | JUSTIN HAWLEY |
Pre-Inspection | 4/10/2023 | Approved | DAVID SCANTLIN |
SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | JUSTIN HAWLEY |
Smoke Detectors | 4/10/2023 | Approved | JUSTIN HAWLEY |