323 N CARMELINA AVE 90049
Certificate Information: 323 N CARMELINA AVE 90049
- Application / Permit
- 22014-30000-00484
- Plan Check / Job No.
- B22WL00454
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel and addition to an existing 2-story S.F.D. with a partial basements expansion
- Permit Issued
- Issued on 10/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | TARIK SAOUD |
| Corrections Issued | 2/19/2022 | TARIK SAOUD |
| Quality Review Completed | 3/8/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/30/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/7/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/12/2022 | APPLICANT |
| Applicant returned to address corrections | 9/26/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/3/2022 | YASHAR EMAMI |
| Plan Check Approved | 10/18/2022 | YASHAR EMAMI |
| Issued | 10/25/2022 | APPLICANT |
| CofO in Progress | 5/5/2025 | KEVIN SARGSYAN |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
| CofO Issued | 5/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/9/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/9/2022 | DENNIS BRAGIN |
| Permit | Cleared | 5/9/2022 | DENNIS BRAGIN |
| Sewer availability | Cleared | 5/9/2022 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2022 | DENNIS BRAGIN |
| Trees in Parkway | Cleared | 6/1/2022 | ADALBERTO VERA |
| Excavation more than 5-ft deep | Cleared | 6/30/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/30/2022 | TARIK SAOUD |
| Low Impact Development | Cleared | 8/10/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | DENNIS BRAGIN |
Contact Information
| Architect | Giannetti,, Stephen Andrew; Lic. No.: C18467 | 851 SADDLE LANE OJAI, CA 93023 |
| Contractor | Jones Builders Group Inc; Lic. No.: 904861-B | 23823 MALIBU RD 50-375 MALIBU, CA 90265 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/31/2022 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 1/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 2/3/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 3/6/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/23/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 4/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 4/24/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/3/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 5/11/2023 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/22/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/29/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/29/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 12/4/2023 | Conditional Approval | KEVIN SARGSYAN |
| HVAC-Rough | 12/5/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/5/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 12/13/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/13/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 12/28/2023 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/3/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/17/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/26/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 1/26/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 2/2/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 2/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 2/8/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/13/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/21/2024 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 9/16/2024 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 9/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 9/16/2024 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 9/17/2024 | Approved | KENNETH NAGLE |
| Sewer | 11/15/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/27/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 4/1/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/2/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 4/3/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 4/3/2025 | Approved | KEVIN SARGSYAN |
| Final | 4/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/30/2025 | Approved | KEVIN SARGSYAN |
| Green Building Final | 4/30/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 4/30/2025 | Approved | KEVIN SARGSYAN |
| Structural Steel Frame | 4/30/2025 | Approved | KEVIN SARGSYAN |
| Final | 5/5/2025 | OK to Issue CofO | KEVIN SARGSYAN |