8213 S RAMSGATE AVE 90045
Certificate Information: 8213 S RAMSGATE AVE 90045
- Application / Permit
- 22014-30000-00389
- Plan Check / Job No.
- B22WL00347
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) SFD. Per engineering design.
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | MANUEL GARCIA |
| Corrections Issued | 2/5/2022 | MANUEL GARCIA |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Applicant returned to address corrections | 3/25/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 5/1/2022 | RICHARD GARCIA |
| Plan Check Approved | 5/11/2022 | RICHARD GARCIA |
| Plan Check Approved | 5/11/2022 | ALFREDO JARA |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 11/15/2023 | RICHARD STEINBACH |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
| CofO Issued | 11/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 3/5/2022 | JOSE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 3/17/2022 | ROBERT HUGHES |
| ZI | Cleared | 3/24/2022 | LOUIS ORTEGA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | R S R Construction; Lic. No.: 853717-B | 10242 PARKINSON AVENUE WHITTIER, CA 90605 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | BOBBY KEY |
| Insulation | 6/15/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 6/15/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | BOBBY KEY |
| Green Building Rough | 7/26/2023 | Approved | BOBBY KEY |
| Insulation | 7/26/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 7/26/2023 | Approved | BOBBY KEY |
| Final | 11/8/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 11/8/2023 | Approved | BOBBY KEY |
| Green Building Final | 11/8/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 11/8/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/15/2023 | Approved | RICHARD STEINBACH |
| Final | 11/15/2023 | OK to Issue CofO | RICHARD STEINBACH |
| HVAC-Final | 11/15/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 11/15/2023 | Approved | RICHARD STEINBACH |