1802 3/4 N MARIPOSA AVE 90027

Certificate Information: 1802 3/4 N MARIPOSA AVE 90027

Application / Permit
22014-30000-00379
Plan Check / Job No.
B22WL00337
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd floor 800 sf ADU addition to a detached garage belonging to an existing multi family bldg per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/25/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 FELIPE HERNANDEZ
Disabled Access Plans Picked Up 3/1/2022 APPLICANT
Corrections Issued 3/7/2022 FELIPE HERNANDEZ
Quality Review Completed 3/16/2022 CHIHARU SUZUKI
Building Plans Picked Up 4/15/2022 APPLICANT
Green Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 2/14/2023 HOOMAN HAJIZADEH
Plan Check Approved 6/13/2024 HOOMAN HAJIZADEH
Issued 7/25/2024 APPLICANT
CofO in Progress 3/12/2025 ENRIQUE MIRELES
Permit Finaled 3/16/2025 DEROLD HAUFF
CofO Issued 3/16/2025 DEROLD HAUFF
Permit Finaled 3/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/2/2022 CINDY QI
Roof/Waste drainage to street Cleared 5/2/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 5/5/2022 CINDY QI
Sewer availability Cleared 5/5/2022 CINDY QI
ZA Case Cleared 5/23/2022 RYAN LY
Tenant Habitability Plan Cleared 5/26/2022 MICHAEL SOTO
Grading Pre-Inspection Cleared 6/16/2022 KIRK LINKLATER
GPI Written Notices Cleared 1/10/2023 FELIPE HERNANDEZ
Green Code Cleared 1/12/2023 MICHAEL AYERS
DAS Clearance Cleared 2/2/2023 FELIPE HERNANDEZ
Specific Plan Cleared 3/3/2023 LIKYELESH ABERA

Contact Information

Architect Youssefzadeh,, Atabak; Lic. No.: C22727 438 S PECK DRIVE      BEVERLY HILLS, CA 90212
Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/11/2024 Partial Approval RAFAEL CORTES
Deputy Drilled-In Anchors 10/25/2024 Partial Approval LUIS CCAMACHO
Deputy Reinf. Concrete 10/25/2024 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 10/25/2024 Partial Approval LUIS CCAMACHO
Green Building Rough 11/8/2024 Approved LUIS CCAMACHO
Wood Frame 11/8/2024 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 11/22/2024 Partial Approval LUIS CCAMACHO
Footing/Foundation/Slab 12/3/2024 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Approved ENRIQUE MIRELES
Wood Frame 12/10/2024 Corrections Issued ENRIQUE MIRELES
Wood Frame 12/23/2024 Corrections Issued ENRIQUE MIRELES
Wood Frame 12/26/2024 Partial Approval ENRIQUE MIRELES
Deputy Wood Construction 12/30/2024 Approved ENRIQUE MIRELES
Insulation 12/30/2024 Approved ENRIQUE MIRELES
Drywall Nailing 1/2/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/7/2025 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 1/13/2025 Partial Approval ANTHONY RAMOS
Final 2/10/2025 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 2/10/2025 Approved ENRIQUE MIRELES
Green Building Final 2/10/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/10/2025 Approved ENRIQUE MIRELES
Wood Frame 2/10/2025 Approved ENRIQUE MIRELES
Final 2/20/2025 Corrections Issued ENRIQUE MIRELES
Final 2/25/2025 Corrections Issued ENRIQUE MIRELES
Final 3/3/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 3/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 3/10/2025 OK to Issue CofO ENRIQUE MIRELES