11921 W FOXBORO DR 90049

Certificate Information: 11921 W FOXBORO DR 90049

Application / Permit
22014-30000-00358
Plan Check / Job No.
B22WL00300
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel by Removing (E) one story single family dwelling & keeping 2' long of portoion of (e) foundation & built new 2-story single family dwelling with roof trusses.
Permit Issued
Issued on 6/6/2022
Issuing Office
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 GARO TELMI
Corrections Issued 2/16/2022 GARO TELMI
Quality Review Completed 2/24/2022 KEN GILL
Building Plans Picked Up 3/1/2022 APPLICANT
Applicant returned to address corrections 4/8/2022 GARO TELMI
Applicant returned to address corrections 5/13/2022 GARO TELMI
Applicant returned to address corrections 5/18/2022 GARO TELMI
Plan Check Approved 5/26/2022 GARO TELMI
Issued 6/6/2022 APPLICANT
CofO in Progress 10/16/2023 OGANES TARAKHCHYAN
Permit Finaled 10/24/2023 DANIEL ORRANTE
CofO Issued 10/24/2023 DANIEL ORRANTE
Permit Finaled 10/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2022 JENSON LEE
Low Impact Development Cleared 3/22/2022 KHAING AYE
Roof/Waste drainage to street Cleared 3/29/2022 JENSON LEE
Specific Plan Cleared 4/7/2022 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 4/11/2022 JENSON LEE
Sewer availability Cleared 4/11/2022 JENSON LEE
Miscellaneous Cleared 4/13/2022 RAYMOND MUGAMBWA
Permit Cleared 4/14/2022 JENSON LEE
Grading Pre-Inspection Cleared 5/20/2022 GARO TELMI

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/18/2022 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/22/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 8/22/2022 Partial Approval KEVIN SARGSYAN
Sewer 8/22/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 9/13/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/15/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 10/14/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 10/25/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/8/2022 Approved KEVIN SARGSYAN
Underground Mechanical 12/8/2022 Approved KEVIN SARGSYAN
Deputy Wood Construction 12/9/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/28/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/12/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 1/17/2023 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 1/17/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/19/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/27/2023 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 2/8/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/9/2023 Partial Approval MICHAEL PELHAM
Shower Pan 2/13/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/16/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Corrections Issued HERBERT GIRON
Deputy Wood Construction 2/28/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/22/2023 No Access for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 3/24/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/10/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 4/17/2023 Not Ready for Inspection JESUS PINEDA
Deputy Drilled-In Anchors 4/17/2023 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/17/2023 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 4/17/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 4/24/2023 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/24/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/24/2023 Partial Approval OGANES TARAKHCHYAN
Insulation 4/26/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/4/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/9/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/31/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/18/2023 Corrections Issued CARLOS MATAMOROS
HVAC-Final 7/18/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 7/18/2023 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 7/19/2023 Approved CARLOS MATAMOROS
HVAC-Final 7/20/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 7/20/2023 Approved CARLOS MATAMOROS
HVAC-Final 7/25/2023 Corrections Issued OGANES TARAKHCHYAN
Service/Power Release 7/25/2023 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 8/1/2023 Approved OGANES TARAKHCHYAN
Green Building Final 8/1/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/1/2023 Approved OGANES TARAKHCHYAN
Final 8/30/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved KEVIN SARGSYAN
Final 10/3/2023 No Access for Inspection OGANES TARAKHCHYAN
Final 10/6/2023 Not Ready for Inspection KEVIN SARGSYAN
Final 10/13/2023 OK to Issue CofO OGANES TARAKHCHYAN