15655 W CASTLEWOODS DR 91403
Certificate Information: 15655 W CASTLEWOODS DR 91403
- Application / Permit
- 22014-30000-00355
- Plan Check / Job No.
- B22WL00294
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [1]CONVERT PORTIONS OF EXISITING DINING ROOM TO 76SF COVERED OUTDOOR PATIO (LESS THAN 5') AND ENCLOSE EXISTING COVERED ENTRY PATIO TO INTERIOR RESIDENTIAL SPACE. NO EXISTING RFA CHANGED (3775SF) . [2] INTERIOR REMODEL OF 1ST AND 2ND FLOORS TO EXISTING SFD. *NO WORK CAN BE PERFORMED OVER THE PROPERTY LINE
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Corrected on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | SUNMIN LEE |
| Corrections Issued | 2/14/2022 | SUNMIN LEE |
| Quality Review Completed | 2/24/2022 | KEN GILL |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Applicant returned to address corrections | 4/4/2022 | SUNMIN LEE |
| Plan Check Approved | 4/13/2022 | SUNMIN LEE |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 7/17/2023 | VINCENT HANLEY |
| CofO Issued-Status Void | 1/12/2024 | JOHN JANSON |
| Permit Finaled-Status Void | 1/12/2024 | JOHN JANSON |
| Re-Activate Permit | 1/17/2024 | JOHN JANSON |
| Permit Finaled | 1/17/2024 | JOHN JANSON |
| CofO Corrected | 1/17/2024 | JOHN JANSON |
| Permit Finaled | 1/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/2/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/2/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/2/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 3/2/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/8/2022 | OLGA AYALA |
| Grading Pre-Inspection | Cleared | 4/11/2022 | SUNMIN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/27/2022 | Approved | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 4/28/2022 | Conditional Approval | MORRIS JACKSON |
| Wood Frame | 6/7/2022 | Partial Approval | ROBERT GOLD |
| Deputy Wood Construction | 6/22/2022 | Conditional Approval | KRISTEN CAUSEY |
| Rough-Elec/Plmb/HVAC | 10/27/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/15/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 11/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/22/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 11/22/2022 | Approved | VINCENT HANLEY |
| Pool Piping | 11/22/2022 | Approved | VINCENT HANLEY |
| Pre-Gunite | 11/22/2022 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 11/22/2022 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 11/28/2022 | Approved | VINCENT HANLEY |
| Insulation | 12/2/2022 | Corrections Issued | VINCENT HANLEY |
| Insulation | 12/7/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/23/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/23/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/23/2022 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/12/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 1/12/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/30/2023 | Approved | VINCENT HANLEY |
| Final | 6/30/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 6/30/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/30/2023 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Final | 6/30/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/30/2023 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 6/30/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/14/2023 | Approved | VINCENT HANLEY |
| Final | 7/14/2023 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 7/14/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/14/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/14/2023 | Approved | VINCENT HANLEY |