116 S HARPER AVE 90048
Certificate Information: 116 S HARPER AVE 90048
- Application / Permit
- 22014-30000-00332
- Plan Check / Job No.
- B22WL00248
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO CREATE A NEW ACCESORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), & 488 SF ADDITION.
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | EDWIN ESPIN |
| Corrections Issued | 2/15/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 6/23/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/19/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | LUIS RINCON |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 4/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/13/2023 | DANIEL ORRANTE |
| CofO Issued | 4/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/3/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 5/5/2022 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 6/9/2022 | MICHAEL SOTO |
| Construction near power lines | Cleared | 9/16/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/16/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/23/2022 | Approved | JEREMY TODD |
| Sewer | 12/23/2022 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 12/28/2022 | Approved | JEREMY TODD |
| METHANE-Barrier | 12/28/2022 | Approved | JEREMY TODD |
| METHANE-Subgrade | 12/28/2022 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 2/3/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Conditional Approval | JEREMY TODD |
| HVAC-Rough | 2/3/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 2/3/2023 | Approved | JEREMY TODD |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 2/7/2023 | Conditional Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | JEREMY TODD |
| Green Building Rough | 2/7/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Rough | 2/7/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 2/7/2023 | Approved | JEREMY TODD |
| Wood Frame | 2/7/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | EVAN COOPER |
| Insulation | 2/16/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 2/23/2023 | Partial Approval | JEREMY TODD |
| Green Building Rough | 2/23/2023 | Not Ready for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 2/23/2023 | Partial Approval | JEREMY TODD |
| Shower Pan | 2/23/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 3/30/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 3/30/2023 | Approved | JEREMY TODD |
| Final | 3/30/2023 | Not Ready for Inspection | JEREMY TODD |
| Gas Test | 3/30/2023 | Approved | JEREMY TODD |
| Green Building Final | 3/30/2023 | Corrections Issued | JEREMY TODD |
| Green Building Rough | 3/30/2023 | Approved | JEREMY TODD |
| HVAC-Final | 3/30/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 3/30/2023 | Corrections Issued | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | JEREMY TODD |
| Service/Power Release | 3/30/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 3/30/2023 | Approved | JEREMY TODD |
| Final | 4/6/2023 | Corrections Issued | DANIEL ORRANTE |
| Green Building Final | 4/6/2023 | Approved | DANIEL ORRANTE |
| Final | 4/13/2023 | OK to Issue CofO | DANIEL ORRANTE |