8819 W PICKFORD ST 90035

Certificate Information: 8819 W PICKFORD ST 90035

Application / Permit
22014-30000-00324
Plan Check / Job No.
B22WL00234
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground Floor Addition and Remodel to (E) 1-Story S.F.D
Permit Issued
Issued on 11/3/2022
Issuing Office
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 DAVID CASTILLO
Corrections Issued 2/18/2022 DAVID CASTILLO
Quality Review Completed 3/7/2022 CHIHARU SUZUKI
Plan Check Approved 6/14/2022 DAVID CASTILLO
Building Plans Picked Up 6/15/2022 APPLICANT
Plan Check Approved 10/27/2022 DAVID CASTILLO
Issued 11/3/2022 APPLICANT
CofO in Progress 10/10/2023 MEL KHACHATOURIAN
Permit Finaled 10/13/2023 DANIEL ORRANTE
CofO Issued 10/13/2023 DANIEL ORRANTE
Permit Finaled 10/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 3/7/2022 JEANIE LAM
Grading Pre-Inspection Cleared 3/10/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 4/12/2022 JEANIE LAM
Sewer availability Cleared 4/12/2022 JEANIE LAM
Trees in Parkway Cleared 5/4/2022 ADALBERTO VERA
Low Impact Development Cleared 5/20/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 5/23/2022 JEANIE LAM
GPI Written Notices Cleared 6/9/2022 CHIHARU SUZUKI

Contact Information

Contractor Soumekh Michael N; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2022 Corrections Issued JEREMY TODD
Footing/Foundation/Slab 1/11/2023 Approved JEREMY TODD
METHANE-Barrier 1/11/2023 Approved JEREMY TODD
METHANE-Subgrade 1/11/2023 Approved JEREMY TODD
Excavation/Setback/Form/Re-Bar 1/25/2023 Corrections Issued JEREMY TODD
PLUMBING-Rough 2/16/2023 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Not Ready for Inspection JEREMY TODD
PLUMBING-Rough 2/21/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved JEREMY TODD
Interior/Exterior Lathing 4/3/2023 Approved JEREMY TODD
Wood Frame 4/3/2023 Approved JEREMY TODD
ELECTRICAL-Rough 4/24/2023 Approved JEREMY TODD
HVAC-Rough 4/24/2023 Approved JEREMY TODD
PLUMBING-Rough 4/24/2023 Not Ready for Inspection JEREMY TODD
BUILDING-Rough-Frame 4/26/2023 Approved JEREMY TODD
Green Building Rough 4/26/2023 Approved JEREMY TODD
METHANE-Rough 4/26/2023 Approved JEREMY TODD
PLUMBING-Rough 4/26/2023 Approved JEREMY TODD
Insulation 5/3/2023 Approved JEREMY TODD
Drywall Nailing 5/8/2023 Approved JEREMY TODD
Interior/Exterior Lathing 5/11/2023 Approved JEREMY TODD
Shower Pan 5/11/2023 Approved JEREMY TODD
Interior/Exterior Lathing 5/16/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Not Ready ARAM AVEDISIAN
ELECTRICAL-Final 8/8/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 8/8/2023 Corrections Issued ARAM AVEDISIAN
HVAC-Final 8/8/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 8/8/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/8/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 8/16/2023 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 8/16/2023 No Access for Inspection MEL KHACHATOURIAN
Service/Power Release 8/16/2023 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 8/18/2023 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 8/18/2023 No Access for Inspection MEL KHACHATOURIAN
Service/Power Release 8/18/2023 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 8/23/2023 Approved MEL KHACHATOURIAN
Final 8/23/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 8/23/2023 Approved MEL KHACHATOURIAN
Final 10/11/2023 OK to Issue CofO MEL KHACHATOURIAN
Green Building Final 10/11/2023 Approved MEL KHACHATOURIAN