8819 W PICKFORD ST 90035
Certificate Information: 8819 W PICKFORD ST 90035
- Application / Permit
- 22014-30000-00324
- Plan Check / Job No.
- B22WL00234
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground Floor Addition and Remodel to (E) 1-Story S.F.D
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | DAVID CASTILLO |
| Corrections Issued | 2/18/2022 | DAVID CASTILLO |
| Quality Review Completed | 3/7/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 6/14/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | DAVID CASTILLO |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 10/10/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 10/13/2023 | DANIEL ORRANTE |
| CofO Issued | 10/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 3/7/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 3/10/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/12/2022 | JEANIE LAM |
| Trees in Parkway | Cleared | 5/4/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 5/20/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | JEANIE LAM |
| GPI Written Notices | Cleared | 6/9/2022 | CHIHARU SUZUKI |
Contact Information
| Contractor | Soumekh Michael N; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/30/2022 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 1/11/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 1/11/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 1/11/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Corrections Issued | JEREMY TODD |
| PLUMBING-Rough | 2/16/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Not Ready for Inspection | JEREMY TODD |
| PLUMBING-Rough | 2/21/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/3/2023 | Approved | JEREMY TODD |
| Wood Frame | 4/3/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 4/24/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 4/24/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/24/2023 | Not Ready for Inspection | JEREMY TODD |
| BUILDING-Rough-Frame | 4/26/2023 | Approved | JEREMY TODD |
| Green Building Rough | 4/26/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 4/26/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/26/2023 | Approved | JEREMY TODD |
| Insulation | 5/3/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 5/8/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 5/11/2023 | Approved | JEREMY TODD |
| Shower Pan | 5/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 5/16/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/8/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/8/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 8/8/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 8/8/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/8/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/16/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 8/16/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Service/Power Release | 8/16/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 8/18/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 8/18/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Service/Power Release | 8/18/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/23/2023 | Approved | MEL KHACHATOURIAN |
| Final | 8/23/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 8/23/2023 | Approved | MEL KHACHATOURIAN |
| Final | 10/11/2023 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 10/11/2023 | Approved | MEL KHACHATOURIAN |