1441 S STEARNS DR 90035
Certificate Information: 1441 S STEARNS DR 90035
- Application / Permit
- 22014-30000-00315
- Plan Check / Job No.
- B22WL00212
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AND MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING. *** 1 of 2 ***
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | JOHNNY WU |
| Corrections Issued | 2/14/2022 | JOHNNY WU |
| Quality Review Completed | 2/17/2022 | FARUK SEZER |
| Applicant returned to address corrections | 3/9/2022 | JOHNNY WU |
| Applicant returned to address corrections | 4/7/2022 | JOHNNY WU |
| Plan Check Approved | 4/8/2022 | JOHNNY WU |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 1/6/2023 | JOSE AVILA |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/11/2022 | JEANIE LAM |
| Green Code | Cleared | 4/7/2022 | JOHNNY WU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/27/2022 | Conditional Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 5/6/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 5/6/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 5/6/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/10/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 5/18/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 6/7/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 6/7/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/9/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 6/9/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 6/9/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/15/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 6/15/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/15/2022 | Approved | JOSE AVILA |
| Wood Frame | 6/15/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 6/17/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 6/23/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | JOSE AVILA |
| METHANE-Rough | 6/23/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | JOSE AVILA |
| Insulation | 6/28/2022 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/28/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 6/28/2022 | Corrections Issued | JOSE AVILA |
| Insulation | 7/5/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JOSE AVILA |
| Shower Pan | 7/5/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/14/2022 | Approved Pending GreenApproval | JOSE AVILA |
| Green Building Rough | 7/14/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/14/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/16/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| Final | 12/16/2022 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JOSE AVILA |
| Green Building Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/16/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 12/16/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/21/2022 | Approved | JOSE AVILA |
| HVAC-Final | 12/21/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/21/2022 | Approved | JOSE AVILA |
| Final | 1/5/2023 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 1/5/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 1/6/2023 | Approved | JOSE AVILA |