1441 S STEARNS DR 90035

Certificate Information: 1441 S STEARNS DR 90035

Application / Permit
22014-30000-00315
Plan Check / Job No.
B22WL00212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AND MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING. *** 1 of 2 ***
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 JOHNNY WU
Corrections Issued 2/14/2022 JOHNNY WU
Quality Review Completed 2/17/2022 FARUK SEZER
Applicant returned to address corrections 3/9/2022 JOHNNY WU
Applicant returned to address corrections 4/7/2022 JOHNNY WU
Plan Check Approved 4/8/2022 JOHNNY WU
Building Plans Picked Up 4/11/2022 APPLICANT
Issued 4/21/2022 APPLICANT
CofO in Progress 1/6/2023 JOSE AVILA
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 2/25/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/28/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 3/11/2022 JEANIE LAM
Green Code Cleared 4/7/2022 JOHNNY WU

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/27/2022 Conditional Approval RUBEN SALAS
Footing/Foundation/Slab 5/6/2022 Corrections Issued JOSE AVILA
METHANE-Barrier 5/6/2022 Approved JOSE AVILA
METHANE-Subgrade 5/6/2022 Approved JOSE AVILA
PLUMBING-Rough 5/10/2022 Corrections Issued JOSE AVILA
Wood Frame 5/18/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved JOSE AVILA
Rough-Elec/Plmb/HVAC 6/7/2022 Corrections Issued JOSE AVILA
Wood Frame 6/7/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/9/2022 Corrections Issued JOSE AVILA
HVAC-Rough 6/9/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/9/2022 Corrections Issued JOSE AVILA
Wood Frame 6/9/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/15/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Corrections Issued JOSE AVILA
HVAC-Rough 6/15/2022 Approved JOSE AVILA
PLUMBING-Rough 6/15/2022 Approved JOSE AVILA
Wood Frame 6/15/2022 Corrections Issued JOSE AVILA
Wood Frame 6/17/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 6/23/2022 Not Ready for Inspection JOSE AVILA
Green Building Rough 6/23/2022 Not Ready for Inspection JOSE AVILA
METHANE-Rough 6/23/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved JOSE AVILA
Insulation 6/28/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 6/28/2022 Corrections Issued JOSE AVILA
Wood Frame 6/28/2022 Corrections Issued JOSE AVILA
Insulation 7/5/2022 Approved JOSE AVILA
Interior/Exterior Lathing 7/5/2022 Approved JOSE AVILA
Shower Pan 7/5/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 7/14/2022 Approved Pending GreenApproval JOSE AVILA
Green Building Rough 7/14/2022 Approved JOSE AVILA
Interior/Exterior Lathing 7/14/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 12/16/2022 Approved JOSE AVILA
ELECTRICAL-Final 12/16/2022 Corrections Issued JOSE AVILA
Final 12/16/2022 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 12/16/2022 Approved JOSE AVILA
Green Building Final 12/16/2022 Corrections Issued JOSE AVILA
HVAC-Final 12/16/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 12/16/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 12/16/2022 Approved JOSE AVILA
ELECTRICAL-Final 12/21/2022 Approved JOSE AVILA
HVAC-Final 12/21/2022 Approved JOSE AVILA
PLUMBING-Final 12/21/2022 Approved JOSE AVILA
Final 1/5/2023 OK to Issue CofO JOSE AVILA
Green Building Final 1/5/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Approved JOSE AVILA
Service/Power Release 1/6/2023 Approved JOSE AVILA