10564 W BLYTHE AVE 90064
Certificate Information: 10564 W BLYTHE AVE 90064
- Application / Permit
- 22014-30000-00308
- Plan Check / Job No.
- B22WL00198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel second story addition of existing one story house *** 1 of 2 ***
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | KAVIAN REFAHI |
| Corrections Issued | 2/17/2022 | KAVIAN REFAHI |
| Quality Review Completed | 3/8/2022 | FELIX FIGUEROA |
| Applicant returned to address corrections | 5/13/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/16/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/1/2022 | KAVIAN REFAHI |
| Plan Check Approved | 8/5/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Issued | 8/17/2022 | APPLICANT |
| CofO in Progress | 9/11/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 9/11/2025 | RICHARD STEINBACH |
| CofO Issued | 9/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/13/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 5/13/2022 | KAVIAN REFAHI |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | DENNIS BRAGIN |
| Sewer availability | Cleared | 5/17/2022 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 7/6/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/21/2022 | DENNIS BRAGIN |
Contact Information
| Architect | , ; Lic. No.: C36916 | 10008 NATIONAL BLVD. #242 LOS ANGELES, CA 90034 |
| Contractor | D U A Build; Lic. No.: 967782-B | 3579 EAST FOOTHILL BLVD #405 PASADENA, CA 91107 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Barrier | 11/17/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 11/17/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/22/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2023 | Approved | JEREMY TODD |
| Deputy Wood Construction | 7/11/2023 | Conditional Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 8/3/2023 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 8/3/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 10/27/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 10/27/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/9/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 11/9/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 11/9/2023 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/9/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 12/1/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 2/14/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 2/14/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/5/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | MEL KHACHATOURIAN |
| Final | 4/22/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 4/22/2025 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 4/22/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 4/22/2025 | Approved | MEL KHACHATOURIAN |
| Final | 7/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Final | 7/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 9/5/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| METHANE-Final | 9/5/2025 | Approved | MEL KHACHATOURIAN |