688 E MILDRED AVE 90291
Certificate Information: 688 E MILDRED AVE 90291
- Application / Permit
- 22014-30000-00160
- Plan Check / Job No.
- B22WL00147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) garage to den and add carport to (E) SFD. All work per WFPP and standard plan. ****Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 05/17/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector MARIAN PODPORA at (213)978-4500 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 767529.****
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 4/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | JASON JANGADA |
| Corrections Issued | 1/22/2022 | JASON JANGADA |
| Applicant returned to address corrections | 6/28/2022 | JASON JANGADA |
| Applicant returned to address corrections | 6/29/2022 | JASON JANGADA |
| Applicant returned to address corrections | 9/28/2022 | ALFREDO JARA |
| Building Plans Picked Up | 10/4/2022 | APPLICANT |
| Plan Check Approved | 2/28/2023 | KHUONG TRUONG |
| Issued | 3/16/2023 | APPLICANT |
| CofO in Progress | 4/7/2023 | ANDREW BEELI |
Permit Application Clearance Information
| Coastal Zone | Cleared | 1/3/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 1/3/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 1/3/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 1/3/2023 | JAZMIN ROQUE |
| Specific Plan | Cleared | 2/9/2023 | PEDRO AYALA |
| Specific Plan | Cleared | 2/9/2023 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 2/13/2023 | SAUL GARCIA |
| Specific Plan | Cleared | 2/13/2023 | JACKSON OLSON |
| ZI | Cleared | 2/13/2023 | JACKSON OLSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | SAUL GARCIA |
| Permit | Cleared | 2/28/2023 | AMAAN MALIK |
Contact Information
| Architect | Butler,, Colleen Janette; Lic. No.: C30035 | 285 W GRAND VIEW AVENUE SIERRA MADRE, CA 91024 |
| Contractor | Alan Goldberg Electric Inc; Lic. No.: 538830-B | 688 OLIVE AVENUE VENICE, CA 90291 |
| Engineer | Schulz,, Les Eric; Lic. No.: S2570 | 346 N LIMA SIERRA MADRE, CA 91024 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2023 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 3/29/2023 | Approved | ANDREW BEELI |
| Footing/Foundation/Slab | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| METHANE-Barrier | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| METHANE-Rough | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| METHANE-Subgrade | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Approved | ANDREW BEELI |
| Wood Frame | 3/29/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 4/3/2023 | Approved | ANDREW BEELI |
| METHANE-Barrier | 4/3/2023 | Approved | ANDREW BEELI |
| METHANE-Subgrade | 4/3/2023 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 4/6/2023 | Approved | ANDREW BEELI |
| Final | 4/6/2023 | OK to Issue CofO | ANDREW BEELI |
| Green Building Final | 4/6/2023 | Approved | ANDREW BEELI |
| Green Building Rough | 4/6/2023 | Approved | ANDREW BEELI |
| METHANE-Final | 4/6/2023 | Approved | ANDREW BEELI |
| METHANE-Rough | 4/6/2023 | Approved | ANDREW BEELI |
| Smoke Detectors | 4/6/2023 | Approved | ANDREW BEELI |