8380 S KENYON AVE 90045
Certificate Information: 8380 S KENYON AVE 90045
- Application / Permit
- 22014-30000-00106
- Plan Check / Job No.
- B22WL00084
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Remodel, 2nd Story Addition with (N) Attached 2-Car Garage to an (E) 1-Story S.F.D
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | CHIHARU SUZUKI |
| Corrections Issued | 2/18/2022 | DAVID CASTILLO |
| Quality Review Completed | 3/7/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Plan Check Approved | 4/15/2022 | DAVID CASTILLO |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 3/20/2023 | BOBBY KEY |
| Permit Finaled | 3/20/2023 | DANIEL ORRANTE |
| CofO Issued | 3/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/16/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | JENSON LEE |
| Specific Plan | Cleared | 3/29/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 4/4/2022 | JOSE HERNANDEZ |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/8/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/9/2022 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 6/9/2022 | Partial Approval | BOBBY KEY |
| Sewer | 6/28/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 6/28/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | HERBERT GIRON |
| Pre-Inspection | 7/5/2022 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/3/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/17/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/13/2022 | Corrections Issued | BOBBY KEY |
| Shower Pan | 9/13/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 9/15/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 9/15/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/15/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/5/2022 | Approved | BOBBY KEY |
| Deputy Wood Construction | 10/6/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/20/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | BOBBY KEY |
| Insulation | 10/26/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 11/17/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/17/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/7/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 2/7/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 2/7/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 3/7/2023 | Partial Approval | BOBBY KEY |
| HVAC-Final | 3/7/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/7/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/7/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/16/2023 | Approved | BOBBY KEY |
| Final | 3/16/2023 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 3/16/2023 | Approved | BOBBY KEY |
| Service/Power Release | 3/16/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 3/16/2023 | Partial Inspection | JESUS PINEDA |