2100 N ERIC DR 90049
Certificate Information: 2100 N ERIC DR 90049
- Application / Permit
- 22014-30000-00027
- Plan Check / Job No.
- B22WL00005
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Remodel and Addition to an (E) 2-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Current Status
- Issued on 10/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | DAVID CASTILLO |
| Corrections Issued | 2/3/2022 | DAVID CASTILLO |
| Quality Review Completed | 2/23/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 8/25/2022 | DAVID CASTILLO |
| Plan Check Approved | 9/21/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Issued | 10/12/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/3/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 6/3/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 6/3/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | JENSON LEE |
| Sewer availability | Cleared | 6/6/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 6/10/2022 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 6/10/2022 | RAYMOND MUGAMBWA |
| Hydrant and Access approval | Cleared | 6/13/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 7/19/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | JENSON LEE |
| GPI Written Notices | Cleared | 9/21/2022 | DAVID CASTILLO |
| Grading Pre-Inspection | Cleared | 9/21/2022 | DAVID CASTILLO |
Contact Information
| Architect | Bleet,, Shawn Randy; Lic. No.: C30269 | 3423 W JEFFERSON BLVD LOS ANGELES, CA 90018 |
| Contractor | Owner-Builder | , |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 10866 WIMER COUNTRY ROAD SUNLAND, CA 91040 |
| Engineer | Crowley,, Jeremiah Michael; Lic. No.: C23325 | 2341 W SILVER LAKE DRIVE LOS ANGELES, CA 90039 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/29/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/3/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 1/27/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 4/11/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 5/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/9/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/14/2023 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/29/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 12/4/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 5/1/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/26/2024 | No Access for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 6/27/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/9/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/11/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/30/2024 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 7/30/2024 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 7/30/2024 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/27/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 10/1/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 10/2/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/2/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | KEVIN SARGSYAN |
| Insulation | 10/29/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/20/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/18/2025 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 4/10/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/17/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/28/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 12/24/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 12/24/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 3/3/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 3/3/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 3/18/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 5/29/2026 | Approved | DAVID SCANTLIN |