7602-7604 N RADFORD AVE 91605
Certificate Information: 7602-7604 N RADFORD AVE 91605
- Application / Permit
- 22014-20001-05526
- Plan Check / Job No.
- B23VN07151
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPLEMENTAL TO 22014-20000-05526 TO CONVERT (E) 18' X 20' ATTACHED GARAGE AND (E) 18' X 10'4" RECREATION ROOM TO (N) SB9 UNIT. WORK DONE PER WFPP. *
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | MADISON ODELL |
| Corrections Issued | 6/10/2023 | MADISON ODELL |
| Quality Review Completed | 6/15/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/12/2023 | APPLICANT |
| Applicant returned to address corrections | 7/13/2023 | MADISON ODELL |
| Applicant returned to address corrections | 7/24/2023 | MADISON ODELL |
| Applicant returned to address corrections | 7/27/2023 | MADISON ODELL |
| Plan Check Approved | 8/8/2023 | MADISON ODELL |
| Issued | 8/10/2023 | APPLICANT |
| Permit Finaled | 5/31/2024 | MATTHEW NELSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Address approval | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Permit | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 7/12/2023 | ANTHONY VARGAS |
| Senate Bill 9 | Cleared | 7/27/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/14/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 8/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/23/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/23/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/7/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/7/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/11/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/11/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 9/11/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/11/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | WILLIAM WREN |
| Insulation | 9/14/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/14/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/19/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/19/2023 | Approved | WILLIAM WREN |
| Gas Test | 10/31/2023 | Approved | DAVID ANDERSON |
| Sewer | 10/31/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/31/2023 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 2/29/2024 | Approved | MATTHEW NELSON |
| Final | 5/9/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/9/2024 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 5/9/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/30/2024 | Approved | MATTHEW NELSON |
| Final | 5/30/2024 | Partial Inspection | MATTHEW NELSON |
| Green Building Final | 5/30/2024 | Partial Approval | MATTHEW NELSON |
| HVAC-Final | 5/30/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/30/2024 | Approved | MATTHEW NELSON |