16027 W LEADWELL ST 91406
Certificate Information: 16027 W LEADWELL ST 91406
- Application / Permit
- 22014-20001-05401
- Plan Check / Job No.
- B24VN01501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 22014-20000-05401. TO REVISE 1 STORY ADDITION TO A (N) 2-STORY ADDITION AND BALCONY TO THE (E) SINGLE FAMILY DWELLING. NFPA 13-D FIRE SPRINKLERS REQUIRED THRU-OUT.
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- Current Status
- Issued on 4/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 2/10/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/14/2024 | ROSENDO MEDINA |
| Plan Check Approved | 3/19/2024 | ROSENDO MEDINA |
| Issued | 4/1/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 3/12/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/13/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 9/10/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 8/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/11/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Wood Frame | 8/20/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 8/28/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 8/28/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 9/9/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 9/12/2025 | Approved | WAYNE REGESTER |
| Insulation | 10/16/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 10/16/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 10/16/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 11/19/2025 | Approved | MICHAEL CORTEZ |