8730 N ENCINO AVE 91325

Certificate Information: 8730 N ENCINO AVE 91325

Application / Permit
22014-20001-05146
Plan Check / Job No.
B23VN02877
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Supplemental Ref to PCIS#: 22014-20001-05146, to " Change Foundation Type from Slab on Grade to Raised Floor and Add New Covered Entry Porch"
Permit Issued
Issued on 4/7/2023
Issuing Office
Current Status
Permit Finaled on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 DAVID CASTILLO
Corrections Issued 3/10/2023 DAVID CASTILLO
Applicant returned to address corrections 3/29/2023 DAVID CASTILLO
Plan Check Approved 4/6/2023 DAVID CASTILLO
Issued 4/7/2023 APPLICANT
Permit Finaled 4/24/2025 CHRISTOPHER ROJAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/20/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/22/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 3/22/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 3/22/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 3/22/2023 MEGAN GODINEZ

Contact Information

Architect Brisley,, Lawrence Kevin; Lic. No.: C19394 11560 NORTHDALE DRIVE      MOORPARK, CA 93021
Architect Brisley,, Lawrence Kevin; Lic. No.: NA19394       ,
Contractor Owner-Builder       ,
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Cox,, Steven Jeffrey; Lic. No.: NA48940       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 7/14/2023 Approved JAVIER RAMOS JR
Insulation 7/14/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 7/14/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 7/20/2023 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 8/10/2023 Conditional Approval JAVIER RAMOS JR
PLUMBING-Rough 8/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 8/14/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 9/8/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 9/8/2023 Corrections Issued JAVIER RAMOS JR
Green Building Rough 9/8/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 9/8/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/29/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 9/29/2023 Approved JAVIER RAMOS JR
Green Building Rough 9/29/2023 Approved JAVIER RAMOS JR
HVAC-Rough 9/29/2023 Approved JAVIER RAMOS JR
Insulation 9/29/2023 Approved JAVIER RAMOS JR
Drywall Nailing 10/18/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/18/2023 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 11/14/2023 Approved JAVIER RAMOS JR
Shower Pan 11/14/2023 Approved JAVIER RAMOS JR
Structural Steel Frame 1/26/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 3/5/2024 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 3/29/2024 Conditional Approval ROBERT GOLD
Pre-Inspection 1/28/2025 Approved JAVIER RAMOS JR
Deputy Steel/Welding 4/4/2025 Conditional Approval RAUL OLAGI