1497-1497 1/2 W 35TH PL 90018

Certificate Information: 1497-1497 1/2 W 35TH PL 90018

Application / Permit
22014-20001-04185
Plan Check / Job No.
B24VN05945
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 22014-10000-04185 TO REVISE WORK DESCRIPTION TO READ "NEW 34'-6" X 41' CARPORT (ON FIRST FLOOR) AND 2 ACCESSORY DWELLING UNITS (ON SECOND FLOOR) PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 5/1/2024
Issuing Office
Valley
Current Status
Permit Finaled on 4/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Plan Check Approved 4/30/2024 SELLA BENYAMIN
Issued 5/1/2024 APPLICANT
Permit Finaled 4/8/2026 SABAS ALONSO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Perjad Construction Inc; Lic. No.: 1043697-B 7267 PACKWOOD TRAIL      LOS ANGELES, CA 90068
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2024 Corrections Issued SABAS ALONSO
Sewer 7/12/2024 Not Ready for Inspection SABAS ALONSO
Deputy Reinf. Concrete 7/16/2024 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/19/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 7/19/2024 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/23/2024 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/14/2024 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 8/14/2024 Corrections Issued CRAIG DAVIS
METHANE-Barrier 8/14/2024 Corrections Issued CRAIG DAVIS
METHANE-Subgrade 8/14/2024 Corrections Issued CRAIG DAVIS
Sewer 8/14/2024 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 8/14/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 8/19/2024 Conditional Approval SABAS ALONSO
Sewer 8/19/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 8/22/2024 Approved SABAS ALONSO
Underground Mechanical 8/22/2024 Partial Approval SABAS ALONSO
Wood Frame 9/16/2024 Corrections Issued SABAS ALONSO
Underground Mechanical 10/8/2024 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 11/20/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 11/20/2024 Corrections Issued SABAS ALONSO
Deputy Wood Construction 11/21/2024 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 11/25/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Approved SABAS ALONSO
HVAC-Rough 11/25/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/25/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/23/2024 Corrections Issued SABAS ALONSO
HVAC-Rough 12/23/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/23/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 12/23/2024 Approved SABAS ALONSO
Shower Pan 12/23/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/6/2025 Corrections Issued SABAS ALONSO
Green Building Rough 1/6/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 1/6/2025 Partial Approval SABAS ALONSO
Shower Pan 1/6/2025 Corrections Issued SABAS ALONSO
Green Building Rough 1/7/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/13/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/22/2025 Approved SABAS ALONSO
Insulation 1/27/2025 Corrections Issued SABAS ALONSO
Insulation 1/30/2025 Approved SABAS ALONSO
Drywall Nailing 3/3/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 3/3/2025 Approved SABAS ALONSO
Shower Pan 4/11/2025 Approved SABAS ALONSO
Gas Test 5/29/2025 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/4/2026 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 2/4/2026 Corrections Issued SABAS ALONSO
Service/Power Release 2/4/2026 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 2/27/2026 Partial Inspection SABAS ALONSO
Final 4/8/2026 Permit Finaled SABAS ALONSO