8359 N DELCO AVE 91306

Certificate Information: 8359 N DELCO AVE 91306

Application / Permit
22014-20001-01380
Plan Check / Job No.
B23VN02350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 22014-20000-01380 TO REVISE SCOPE OF WORK TO 2-STORY ADU
Permit Issued
Issued on 6/2/2023
Issuing Office
Valley
Current Status
Issued on 6/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 JESSE ARELLANO
Corrections Issued 3/5/2023 JESSE ARELLANO
Building Plans Picked Up 3/9/2023 APPLICANT
Plan Check Approved 6/2/2023 ALEC MOUSAKHANIAN
Issued 6/2/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/16/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/16/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/16/2023 CARLOS AGUILERA
Sewer availability Cleared 3/16/2023 CARLOS AGUILERA
Construction near power lines Cleared 5/8/2023 PATRICK MAGALLANES

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/23/2023 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/31/2023 Corrections Issued CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/5/2023 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 9/5/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 10/19/2023 Corrections Issued JEFFREY HARTLINE
Green Building Rough 10/19/2023 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 11/22/2023 Corrections Issued JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Approved JEFFREY HARTLINE
HVAC-Rough 11/22/2023 Corrections Issued JEFFREY HARTLINE
PLUMBING-Rough 11/22/2023 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 12/8/2023 Approved JEFFREY HARTLINE
HVAC-Rough 12/8/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/8/2023 Approved JEFFREY HARTLINE
Wood Frame 12/8/2023 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 1/23/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/23/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/23/2024 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 1/23/2024 Approved JEFFREY HARTLINE
Insulation 5/2/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 5/9/2025 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 5/14/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 5/15/2025 Approved JEFFREY HARTLINE
Final 2/24/2026 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 2/24/2026 Approved JEFFREY HARTLINE
Green Building Final 2/24/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 2/24/2026 Not Ready for Inspection JEFFREY HARTLINE
Final 3/10/2026 Corrections Issued JEFFREY HARTLINE
Green Building Final 3/10/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 3/10/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Final 5/29/2026 Approved JEFFREY HARTLINE
Final 5/29/2026 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 5/29/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 5/29/2026 Approved JEFFREY HARTLINE