18333-18335 W DEVONSHIRE ST 91325

Certificate Information: 18333-18335 W DEVONSHIRE ST 91325

Application / Permit
22014-20000-06402
Plan Check / Job No.
B22VN16571
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW 21'6" X 23'6" ONE STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33.(C) AND (D) ADDITION TO EXISTING SFD WITH ATTACHED GARAGE , NFPA-13R FIRE SPRINKLERS ARE REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING- SEE COMMENTS
Permit Issued
Issued on 4/10/2023
Issuing Office
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 RARES BODEA
Corrections Issued 1/4/2023 RARES BODEA
Quality Review Completed 1/12/2023 STEVEN KIM
Plan Check Approved 4/6/2023 RARES BODEA
Issued 4/10/2023 APPLICANT
CofO in Progress 8/13/2025 DAVID SCANTLIN
Permit Finaled 10/2/2025 MICHAEL PELHAM
CofO Issued 10/2/2025 MICHAEL PELHAM
Permit Finaled 10/2/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 2/15/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/16/2023 CARLOS AGUILERA
Sewer availability Cleared 2/16/2023 CARLOS AGUILERA
Low Impact Development Cleared 3/21/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 3/21/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2023 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 1/19/2024 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 1/19/2024 Partial Approval MORRIS JACKSON
Green Building Rough 1/19/2024 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 1/19/2024 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 1/19/2024 Approved MORRIS JACKSON
Deputy Wood Construction 2/1/2024 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Approved DAVID SCANTLIN
HVAC-Rough 2/7/2024 Approved DAVID SCANTLIN
Wood Frame 2/7/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 3/18/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/18/2024 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 3/28/2024 Approved DAVID SCANTLIN
Green Building Rough 3/28/2024 Approved DAVID SCANTLIN
Insulation 3/28/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 3/28/2024 Approved DAVID SCANTLIN
Drywall Nailing 4/16/2024 Conditional Approval KRISTEN CAUSEY
Shower Pan 4/16/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 5/7/2024 Approved KRISTEN CAUSEY
Drywall Nailing 8/12/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 8/12/2025 Approved DAVID SCANTLIN
Final 8/12/2025 OK to Issue CofO DAVID SCANTLIN
Footing/Foundation/Slab 8/12/2025 Approved DAVID SCANTLIN
Green Building Final 8/12/2025 Approved DAVID SCANTLIN
HVAC-Final 8/12/2025 Approved DAVID SCANTLIN
PLUMBING-Final 8/12/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 8/12/2025 Approved DAVID SCANTLIN
Service/Power Release 8/13/2025 Approved DAVID SCANTLIN