401 N SURFVIEW DR 90272

Certificate Information: 401 N SURFVIEW DR 90272

Application / Permit
22014-20000-06356
Plan Check / Job No.
B22VN19084
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL; ADD NEW 12' x 15' PATIO WITH DECK ABOVE
Permit Issued
Issued on 6/6/2023
Issuing Office
Valley
Current Status
Issued on 6/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 SELLA BENYAMIN
Corrections Issued 2/7/2023 SELLA BENYAMIN
Quality Review Completed 2/10/2023 STEVEN KIM
Building Plans Picked Up 2/10/2023 APPLICANT
Plan Check Approved 5/25/2023 SELLA BENYAMIN
Issued 6/6/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2023 JENSON LEE
Roof/Waste drainage to street Cleared 3/1/2023 JENSON LEE
Grading Pre-Inspection Cleared 3/3/2023 MICHAEL TEMPLE
Coastal Zone Cleared 3/14/2023 SPENCER WEJROWSKI

Contact Information

Contractor Shaddick Construction; Lic. No.: 891974-B 4147 SHADY GLADE AVE      STUDIO CITY, CA 91604
Engineer Hanna,, Arsanious Michael; Lic. No.: C70743 13408 NAOMA LN      CERRITOS, CA 90703

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2023 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 10/10/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/6/2023 Approved EVAN COOPER
Footing/Foundation/Slab 11/6/2023 Approved EVAN COOPER
HVAC-Rough 11/6/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 11/6/2023 Corrections Issued EVAN COOPER
Deputy Reinf. Concrete 11/8/2023 Conditional Approval EVAN COOPER
Wood Frame 11/8/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 11/30/2023 Approved EVAN COOPER
Interior/Exterior Lathing 11/30/2023 Partial Approval EVAN COOPER
Shower Pan 11/30/2023 Approved EVAN COOPER
HVAC-Rough 12/4/2023 Corrections Issued EVAN COOPER
Insulation 12/4/2023 Approved EVAN COOPER
Interior/Exterior Lathing 12/6/2023 Partial Approval MICHAEL PELHAM
Drywall Nailing 12/21/2023 Approved EVAN COOPER
ELECTRICAL-Final 10/10/2024 Approved EVAN COOPER
Final 10/10/2024 Conditional Approval EVAN COOPER
HVAC-Final 10/10/2024 Approved EVAN COOPER
PLUMBING-Final 10/10/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 10/10/2024 Approved EVAN COOPER