15707-15709 W CELTIC ST 91344

Certificate Information: 15707-15709 W CELTIC ST 91344

Application / Permit
22014-20000-06353
Plan Check / Job No.
B22VN19075
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
29' X 15'-9" IRREGULAR SHAPED ADDITION TO AND CONVERT (E) 8' X 18' PORTION OF (E) ATTACHED CARPORT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). WORK PER WFPP.
Permit Issued
Issued on 3/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 12/30/2022 SERGIO MUNIZ
Corrections Issued 12/31/2022 SERGIO MUNIZ
Building Plans Picked Up 1/6/2023 APPLICANT
Plan Check Approved 3/8/2023 OMAR GARNICA
Issued 3/9/2023 APPLICANT
CofO in Progress 3/22/2024 JENNIFER RABUCHIN
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/30/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/30/2023 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 1/30/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/30/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 1/30/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/1/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/11/2023 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/29/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/23/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 10/23/2023 Approved JAVIER RAMOS JR
Green Building Rough 10/23/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/23/2023 Approved JAVIER RAMOS JR
Wood Frame 10/23/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 11/8/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 11/8/2023 Partial Approval JAVIER RAMOS JR
Sewer 11/8/2023 Approved JAVIER RAMOS JR
Shower Pan 11/8/2023 Approved JAVIER RAMOS JR
Underground Mechanical 11/8/2023 Partial Approval JAVIER RAMOS JR
Wood Frame 11/8/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/29/2023 Approved JAVIER RAMOS JR
HVAC-Rough 11/29/2023 Approved JAVIER RAMOS JR
Insulation 11/29/2023 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 11/29/2023 Approved JAVIER RAMOS JR
Drywall Nailing 12/6/2023 Approved JAVIER RAMOS JR
Insulation 12/6/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/6/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/26/2024 Approved JAVIER RAMOS JR
Final 2/26/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/26/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 2/26/2024 Approved JAVIER RAMOS JR
MERV13>=Final 2/26/2024 Approved JAVIER RAMOS JR
MERV13>=Rough 2/26/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/26/2024 Approved JAVIER RAMOS JR
Final 3/13/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/13/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/22/2024 Approved JENNIFER RABUCHIN
Final 3/22/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/22/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/22/2024 Approved JENNIFER RABUCHIN