6245 1/2 N WILKINSON AVE 91606
Certificate Information: 6245 1/2 N WILKINSON AVE 91606
- Application / Permit
- 22014-20000-06329
- Plan Check / Job No.
- B22VN19011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing 459 Sq Ft Detached Garage to ADU WITH 342SQFT ADDTION PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2023 | KHUONG TRUONG |
| Corrections Issued | 1/5/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 5/30/2023 | HANS SANTIAGO |
| Plan Check Approved | 7/6/2023 | WEIJIAN HUANG |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 9/5/2025 | WAYNE REGESTER |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
| CofO Issued | 9/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/11/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/20/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 5/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 5/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 5/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 5/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Wood Frame | 5/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 5/15/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 5/15/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/20/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 5/20/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/23/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 5/29/2025 | Corrections Issued | LOUIS ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 8/21/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 8/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/27/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 9/4/2025 | OK to Issue CofO | WAYNE REGESTER |
| HVAC-Final | 9/4/2025 | Approved | WAYNE REGESTER |
| Service/Power Release | 9/4/2025 | Approved | WAYNE REGESTER |