10410 N ORION AVE 91345

Certificate Information: 10410 N ORION AVE 91345

Application / Permit
22014-20000-06328
Plan Check / Job No.
B22VN19009
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT EXISTING DETACHED CAR GARAGE(338 SQ.FT.) INTO A NEW DETACHED ADU WITH 159 SQ.FT. ADDITION PER LAMC 12.22 A 33 (c)-(d)
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 OMAR GARNICA
Corrections Issued 1/6/2023 OMAR GARNICA
Applicant returned to address corrections 4/12/2023 ARSALAN SHABESTARI
Plan Check Approved 4/16/2023 ANDREW SANTIAGO
Issued 4/17/2023 APPLICANT
CofO in Progress 4/25/2024 JENNIFER RABUCHIN
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/12/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/12/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/18/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/18/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/10/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2023 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/12/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/12/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/21/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/21/2023 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 8/1/2023 Approved ROBERT GOLD
Footing/Foundation/Slab 8/1/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 11/15/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/15/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 11/15/2023 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 11/15/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/15/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 11/15/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/15/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/20/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 11/20/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/20/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/22/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Approved JENNIFER RABUCHIN
Green Building Rough 11/22/2023 Approved JENNIFER RABUCHIN
Insulation 11/22/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 11/22/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/22/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 12/4/2023 Approved THOMAS FINNILA
Drywall Nailing 12/7/2023 No Access for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 No Access for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 1/22/2024 Approved JENNIFER RABUCHIN
Service/Power Release 3/7/2024 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 3/11/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/11/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 3/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 3/11/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/19/2024 Corrections Issued JENNIFER RABUCHIN
Final 3/19/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/19/2024 Approved JENNIFER RABUCHIN
HVAC-Final 3/19/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 3/19/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 3/19/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 3/26/2024 Approved JENNIFER RABUCHIN
Final 3/26/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 3/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 3/26/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/28/2024 Approved JENNIFER RABUCHIN
Final 3/28/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/28/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/28/2024 Approved JENNIFER RABUCHIN
Service/Power Release 3/28/2024 Approved JENNIFER RABUCHIN