2511 S PURDUE AVE 90064

Certificate Information: 2511 S PURDUE AVE 90064

Application / Permit
22014-20000-06323
Plan Check / Job No.
B22VN18984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 11"2 X 14' ADDITION TO (E) SFD FOR NEW BATHROOM , ENCLOSE (E) 13' X 11'2" PATIO COVER FOR NEW MASTER BEDROOM , INTERIOR REMODEL TO CONVERT PORTION OF (E) LIVING ROOM TO NEW CLOSET, ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/17/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 RARES BODEA
Corrections Issued 2/15/2023 RARES BODEA
Quality Review Completed 2/23/2023 STEVEN KIM
Building Plans Picked Up 2/24/2023 APPLICANT
Plan Check Approved 5/8/2023 RARES BODEA
Issued 5/17/2023 APPLICANT
CofO in Progress 10/9/2024 KIRK SANDERS
CofO Issued 10/30/2024 RICHARD STEINBACH
Permit Finaled 10/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 3/5/2023 JIMMY VIVAR
Roof/Waste drainage to street Cleared 3/10/2023 JASON NG
Stormwater Pollution Mitigatn Cleared 4/28/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 5/1/2023 JASON NG
Sewer availability Cleared 5/1/2023 JASON NG

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Contractor Silverstone General Builder; Lic. No.: 950719-B 3293 HEATHER FIELD DR      HACIENDA HTS, CA 91745

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/27/2023 Partial Approval JESUS PINEDA
Sewer 6/27/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 7/20/2023 Approved JEREMY TODD
PLUMBING-Rough 10/6/2023 Partial Approval CLAYTON GRAHAM
Wood Frame 10/6/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Approved BEN MOLSTAD
PLUMBING-Rough 11/3/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 11/28/2023 Approved BEN MOLSTAD
Shower Pan 11/28/2023 Approved BEN MOLSTAD
Insulation 12/7/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 12/7/2023 Approved BEN MOLSTAD
Wood Frame 12/7/2023 Approved BEN MOLSTAD
Drywall Nailing 12/18/2023 Approved BEN MOLSTAD
Green Building Rough 12/18/2023 Approved BEN MOLSTAD
Service/Power Release 1/4/2024 Corrections Issued KENNETH NAGLE
Interior/Exterior Lathing 1/9/2024 Approved BEN MOLSTAD
Service/Power Release 1/9/2024 Not Ready for Inspection BEN MOLSTAD
Interior/Exterior Lathing 2/23/2024 Partial Inspection KENNETH NAGLE
ELECTRICAL-Final 4/10/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 4/16/2024 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 5/8/2024 Approved ASHLEY THOMPSON
Smoke Detectors 5/8/2024 Corrections Issued ASHLEY THOMPSON
Service/Power Release 5/9/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/31/2024 Approved KIRK SANDERS
Final 5/31/2024 Corrections Issued KIRK SANDERS
Green Building Final 5/31/2024 Not Ready for Inspection KIRK SANDERS
MERV13>=Final 5/31/2024 Not Ready for Inspection KIRK SANDERS
MERV13>=Rough 5/31/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 5/31/2024 Corrections Issued KIRK SANDERS
Final 9/4/2024 Corrections Issued KIRK SANDERS
MERV13>=Final 9/4/2024 Approved KIRK SANDERS
Final 10/7/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 10/7/2024 Not Ready for Inspection DANIEL VERA
Smoke Detectors 10/7/2024 Not Ready for Inspection DANIEL VERA
Final 10/8/2024 OK to Issue CofO KIRK SANDERS
Green Building Final 10/8/2024 Approved KIRK SANDERS
Smoke Detectors 10/8/2024 Approved KIRK SANDERS