2509 S PURDUE AVE 90064
Certificate Information: 2509 S PURDUE AVE 90064
- Application / Permit
- 22014-20000-06322
- Plan Check / Job No.
- B22VN18984
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'11" X 16'5" TWO STORY ADDITION TO AND CONVERT (E) 18'3" X 18'4" DETACHED GARAGE TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (D), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | RARES BODEA |
| Corrections Issued | 2/15/2023 | RARES BODEA |
| Quality Review Completed | 2/23/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/24/2023 | APPLICANT |
| Plan Check Approved | 5/8/2023 | RARES BODEA |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 10/16/2024 | KIRK SANDERS |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/5/2023 | JIMMY VIVAR |
| Address approval | Cleared | 3/9/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2023 | JASON NG |
| Sewer availability | Cleared | 3/10/2023 | JASON NG |
| Construction near power lines | Cleared | 4/14/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 4/28/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/1/2023 | JASON NG |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Silverstone General Builder; Lic. No.: 950719-B | 3293 HEATHER FIELD DR HACIENDA HTS, CA 91745 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/30/2023 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 6/6/2023 | Partial Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 6/8/2023 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 6/14/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 7/20/2023 | Approved | JEREMY TODD |
| Wood Frame | 10/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Gas Test | 11/3/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 11/3/2023 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/28/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Shower Pan | 11/28/2023 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/1/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 12/1/2023 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 12/8/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 12/8/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 12/8/2023 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 12/8/2023 | Approved | BEN MOLSTAD |
| HVAC-Rough | 12/21/2023 | Partial Approval | BEN MOLSTAD |
| Insulation | 12/21/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/4/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 1/4/2024 | Partial Inspection | BEN MOLSTAD |
| Green Building Rough | 1/4/2024 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 1/4/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 1/4/2024 | Partial Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/9/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 1/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/23/2024 | Partial Inspection | KENNETH NAGLE |
| ELECTRICAL-Final | 4/10/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 4/16/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/8/2024 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 5/8/2024 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 5/31/2024 | Approved | KIRK SANDERS |
| Final | 5/31/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 5/31/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 5/31/2024 | Approved | KIRK SANDERS |
| Final | 6/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 6/12/2024 | Corrections Issued | HERBERT GIRON |
| MERV13>=Final | 6/12/2024 | Corrections Issued | HERBERT GIRON |
| Final | 9/4/2024 | Corrections Issued | KIRK SANDERS |
| MERV13>=Final | 9/4/2024 | Approved | KIRK SANDERS |
| Final | 10/7/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 10/7/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 10/8/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 10/8/2024 | Approved | KIRK SANDERS |
| Final | 10/15/2024 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 10/15/2024 | Approved | KIRK SANDERS |