109 N VISTA ST 90036

Certificate Information: 109 N VISTA ST 90036

Application / Permit
22014-20000-06313
Plan Check / Job No.
B22VN18966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-7" X 18'-8" IRR. ADDITION TO AND CONVERT THE (E) 18' X 20' DET. GARAGE TO AN ACCESSORY DWELLING UNIT, PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 9/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 LUIS RINCON
Corrections Issued 12/31/2022 LUIS RINCON
Building Plans Picked Up 1/11/2023 APPLICANT
Plan Check Approved 3/14/2023 ANGELICA MARTINEZ
Issued 9/13/2023 APPLICANT
CofO in Progress 6/25/2024 AMIR NAZARIAN
CofO Issued 7/15/2024 DEROLD HAUFF
Permit Finaled 7/15/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 1/23/2023 DAMIAN GATTO
ZI Cleared 1/23/2023 DAMIAN GATTO
ZI Cleared 1/23/2023 DAMIAN GATTO
Address approval Cleared 2/22/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 2/22/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 2/28/2023 AMAAN MALIK
Sewer availability Cleared 2/28/2023 AMAAN MALIK
Construction near power lines Cleared 3/6/2023 TINA MIRANDA

Contact Information

Contractor Ground Up Builders; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411
Engineer Chen,, Daniel; Lic. No.: C77440 160 E COMMERCIAL STREET      SAN DIMAS, CA 91773

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/2/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 11/3/2023 Corrections Issued LILIANA PORTILLO
METHANE-Barrier 11/3/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 11/3/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 11/3/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 11/27/2023 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 12/1/2023 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 12/5/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/18/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/19/2024 Not Ready for Inspection LILIANA PORTILLO
Sewer 1/19/2024 Approved LILIANA PORTILLO
Underground Mechanical 1/19/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 2/2/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval LILIANA PORTILLO
HVAC-Rough 2/2/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 2/2/2024 Corrections Issued LILIANA PORTILLO
Wood Frame 2/12/2024 Approved AMIR NAZARIAN
Insulation 3/5/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 3/5/2024 Approved AMIR NAZARIAN
Insulation 3/8/2024 Corrections Issued AMIR NAZARIAN
Insulation 3/14/2024 Approved AMIR NAZARIAN
Shower Pan 3/18/2024 Approved AMIR NAZARIAN
Drywall Nailing 3/26/2024 Approved JEFFREY MEAD
Green Building Rough 3/26/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 4/3/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 6/13/2024 Approved AMIR NAZARIAN
Final 6/13/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 6/13/2024 Approved AMIR NAZARIAN
METHANE-Final 6/13/2024 Approved AMIR NAZARIAN
METHANE-Rough 6/13/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 6/13/2024 Approved AMIR NAZARIAN
Pre-Inspection 6/18/2024 Partial Approval AMIR NAZARIAN
Final 6/24/2024 OK to Issue CofO AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved AMIR NAZARIAN