7851 N AGNES AVE 91605
Certificate Information: 7851 N AGNES AVE 91605
- Application / Permit
- 22014-20000-06304
- Plan Check / Job No.
- B22VN18951
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan ADDITION TO REAR OF (E) SFD. ENCLOSE EXISTING COVERED PATIO (317 SF) AND CONVERT (E) DINING AREA TO CREATE NEW BEDROOM. ALL NEW WINDOW CHANGEOUTS, AND NEW CENTRAL HVAC. ALL WORK TO BE PER WOOD FRAME PRESCRIPTIVE PROVISIONS (WFPP).
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- Current Status
- CofO Issued on 8/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/28/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/10/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/17/2023 | FARSHAD ALIMOHAMADI |
| Issued | 1/19/2023 | APPLICANT |
| CofO in Progress | 5/2/2023 | MATTHEW NELSON |
| Permit Finaled | 8/28/2023 | RUBEN SALAS |
| CofO Issued | 8/28/2023 | RUBEN SALAS |
| Permit Finaled | 8/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 1/5/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/5/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 1/5/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 1/5/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 1/5/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2023 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/31/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/14/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 3/14/2023 | Partial Approval | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 3/28/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 3/28/2023 | Approved | MATTHEW NELSON |
| Insulation | 3/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/31/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/3/2023 | Approved | WILLIAM WREN |
| Shower Pan | 4/5/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/18/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | MATTHEW NELSON |
| Final | 4/27/2023 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/27/2023 | Approved | MATTHEW NELSON |