10439 N OKLAHOMA AVE 91311

Certificate Information: 10439 N OKLAHOMA AVE 91311

Application / Permit
22014-20000-06302
Plan Check / Job No.
B22VN18949
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan NEW GROUND FLOOR ADDITION TO (E) 1-STORY SFD WITH INTERIOR AND EXTERIOR STR. REMODEL AND NEW ATT. TRELLIS.
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
Issued on 5/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 MAHNAZ NOURHASHEMI
Corrections Issued 2/5/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 2/10/2023 GARO TELMI
Applicant returned to address corrections 9/27/2023 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 4/26/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 4/26/2024 MAHNAZ NOURHASHEMI
Issued 5/9/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/25/2023 MICHAEL TEMPLE
Sewer availability Cleared 10/14/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/16/2023 NIKKI ZULUETA
Stormwater Pollution Mitigatn Cleared 3/25/2024 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/5/2024 BRYAN GODINEZ
GPI Written Notices Cleared 4/26/2024 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: NA80632       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/22/2024 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 5/28/2024 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 5/28/2024 Partial Approval DAVID SCANTLIN
Deputy Steel/Welding 6/24/2024 Conditional Approval DAVID SCANTLIN
Deputy Steel/Welding 6/27/2024 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Partial Approval DAVID SCANTLIN
Deputy Steel/Welding 7/12/2024 Conditional Approval DAVID SCANTLIN
BUILDING-Rough-Frame 7/26/2024 Partial Approval DAVID SCANTLIN
Deputy Wood Construction 7/26/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 7/26/2024 Approved DAVID SCANTLIN
HVAC-Rough 7/26/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 7/26/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/1/2024 Approved DAVID SCANTLIN
Green Building Rough 8/1/2024 Approved DAVID SCANTLIN
Insulation 8/1/2024 Approved DAVID SCANTLIN
Drywall Nailing 8/6/2024 Approved SCOTT SOBEL
Interior/Exterior Lathing 8/30/2024 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 9/3/2024 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 9/27/2024 Approved DAVID SCANTLIN
Shower Pan 9/27/2024 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 12/17/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 5/7/2025 Approved DAVID SCANTLIN
HVAC-Final 5/7/2025 Approved DAVID SCANTLIN
PLUMBING-Final 5/7/2025 Approved DAVID SCANTLIN