10351 N BARTEE AVE 91331

Certificate Information: 10351 N BARTEE AVE 91331

Application / Permit
22014-20000-06296
Plan Check / Job No.
B22VN18948
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ONE STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/27/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 12/28/2022 SELLA BENYAMIN
Corrections Issued 12/28/2022 SELLA BENYAMIN
Applicant returned to address corrections 1/6/2023 MICHAEL LOPEZ
Plan Check Approved 1/27/2023 SELLA BENYAMIN
Issued 1/27/2023 APPLICANT
CofO in Progress 4/2/2024 JENNIFER RABUCHIN
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/4/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/4/2023 LEE GUILBEAUX
Sewer availability Cleared 1/4/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/14/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/21/2023 Approved JENNIFER RABUCHIN
METHANE-Barrier 4/21/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 4/21/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/17/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/17/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved JENNIFER RABUCHIN
Green Building Rough 7/17/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 7/17/2023 Approved JENNIFER RABUCHIN
METHANE-Rough 7/17/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/17/2023 Approved JENNIFER RABUCHIN
Insulation 7/27/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/27/2023 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 8/7/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/26/2023 Approved JENNIFER RABUCHIN
Final 12/26/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/26/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 12/26/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 12/26/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 12/26/2023 Approved JENNIFER RABUCHIN
Final 2/27/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 4/2/2024 Approved JENNIFER RABUCHIN
Final 4/2/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/2/2024 Approved JENNIFER RABUCHIN
HVAC-Final 4/2/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/2/2024 Approved JENNIFER RABUCHIN