6955-6957 N CALHOUN AVE 91405

Certificate Information: 6955-6957 N CALHOUN AVE 91405

Application / Permit
22014-20000-06277
Plan Check / Job No.
B22VN18944
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPlan: Ground Floor Addition and Coversion of (E) Attached Garageto ADU per LAMC 12.22 A.33(c) amd (e), and WFPP
Permit Issued
Issued on 5/9/2023
Issuing Office
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/10/2023 DAVID CASTILLO
Corrections Issued 1/11/2023 DAVID CASTILLO
Applicant returned to address corrections 3/2/2023 DAVID CASTILLO
Applicant returned to address corrections 3/29/2023 DAVID CASTILLO
Applicant returned to address corrections 4/17/2023 JASON JANGADA
Plan Check Approved 4/29/2023 JASON JANGADA
Issued 5/9/2023 APPLICANT
CofO in Progress 3/18/2024 RYAN SALAZAR
Permit Finaled 4/1/2024 DANIEL ORRANTE
CofO Issued 4/1/2024 DANIEL ORRANTE
Permit Finaled 4/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/1/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/2/2023 MEGAN GODINEZ
Sewer availability Cleared 2/2/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2023 Approved RYAN SALAZAR
PLUMBING-Rough 6/15/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/20/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 7/20/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/26/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/1/2023 Approved RYAN SALAZAR
HVAC-Rough 8/1/2023 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 8/1/2023 Partial Approval RYAN SALAZAR
Insulation 8/17/2023 Approved RYAN SALAZAR
Drywall Nailing 8/30/2023 Approved RYAN SALAZAR
Underground Mechanical 8/30/2023 Approved RYAN SALAZAR
Service/Power Release 12/15/2023 Not Ready for Inspection RYAN SALAZAR
Final 2/12/2024 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/12/2024 Approved RYAN SALAZAR
Final 2/15/2024 Partial Inspection JOHN COLEMAN
Final 3/13/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 3/15/2024 Approved RYAN SALAZAR