4910 N NOMAD DR 91364

Certificate Information: 4910 N NOMAD DR 91364

Application / Permit
22014-20000-06264
Plan Check / Job No.
B22VN18867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18' X 21' DECK AND PATIO COVER ADDITION TO (E) SFD WITH ATTACHED DECK. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2022 APPLICANT
Assigned to Plan Check Engineer 12/28/2022 JESSE ARELLANO
Corrections Issued 12/28/2022 JESSE ARELLANO
Building Plans Picked Up 1/9/2023 APPLICANT
Plan Check Approved 2/3/2023 GURUNATH NESARAJAH
Issued 2/7/2023 APPLICANT
CofO in Progress 8/28/2024 JOHN HAYES
CofO in Progress 8/29/2024 JOHN HAYES
Permit Finaled 9/25/2024 JOHN JANSON
CofO Issued 9/25/2024 JOHN JANSON
Permit Finaled 9/25/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/25/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/25/2023 DAGOVERTO GUERRERO

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor D L R Construction; Lic. No.: 1002448-B 115 W CALIFORNIA BLVD 467      PASADENA, CA 91105

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/3/2023 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/7/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 8/7/2023 Approved SEAN HAUPT
Structural Steel Frame 8/7/2023 Approved SEAN HAUPT
Wood Frame 9/19/2023 Approved PETER FOLLING
Pre-Inspection 12/7/2023 Partial Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval JOHN KIDWELL
Masonry Wall/Backfill 12/21/2023 Partial Approval JOHN KIDWELL
Insulation 2/6/2024 Corrections Issued JOHN KIDWELL
Drywall Nailing 2/13/2024 Corrections Issued MORRIS JACKSON
Final 5/22/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/22/2024 Not Ready for Inspection JOHN HAYES
Final 6/25/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 6/25/2024 Not Ready for Inspection JOHN HAYES
Final 8/2/2024 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved JOHN HAYES
Smoke Detectors 8/2/2024 Approved JOHN HAYES
Final 8/8/2024 OK to Issue CofO JOHN HAYES