11443 W HORTENSE ST 91602
Certificate Information: 11443 W HORTENSE ST 91602
- Application / Permit
- 22014-20000-06242
- Plan Check / Job No.
- B22VN18798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DET 2-CAR GARAGE (18'X18') INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH IRR SHAPED (27'5"X39') ADDN. ALL WORK PER ENGR.
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 12/23/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/12/2023 | APPLICANT |
| Applicant returned to address corrections | 4/21/2023 | JESSE ARELLANO |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 7/22/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 2/6/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/8/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/22/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/22/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 2/23/2023 | CHRISTIAN PEARSON |
| Specific Plan | Cleared | 2/23/2023 | CHRISTIAN PEARSON |
| Construction near power lines | Cleared | 4/15/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2023 | Partial Inspection | DAVID MATSON |
| PLUMBING-Rough | 7/12/2023 | Partial Approval | JACK KARGODORIAN |
| Sewer | 7/12/2023 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 8/1/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 8/2/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 8/3/2023 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/3/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 9/19/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 9/19/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/3/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/9/2023 | Corrections Issued | JOHN COLEMAN |
| Insulation | 11/15/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 11/15/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 11/22/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/14/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/29/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 5/29/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/29/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/29/2024 | Approved | CHRISTOPHER ROJAS |