10564 N LAUREL CANYON BLVD 91331
Certificate Information: 10564 N LAUREL CANYON BLVD 91331
- Application / Permit
- 22014-20000-06240
- Plan Check / Job No.
- B22VN18793
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 10' X 13' ADDITION TO (E) SINGLE-FAMILY DWELLING TO CREATE (N) HALF- BATHROOM AND LAUNDRY ROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 12/22/2022 | ALEC MOUSAKHANIAN |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 9/27/2023 | MICHEL ABAJAN |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/22/2022 | RYAN KIM |
| Sewer availability | Cleared | 12/22/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2022 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/7/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/10/2023 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 2/10/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/10/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/11/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/11/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/11/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/11/2023 | Approved | MICHEL ABAJAN |
| Insulation | 6/22/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/22/2023 | Approved | MICHEL ABAJAN |
| Insulation | 7/3/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/17/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/26/2023 | Approved | MICHEL ABAJAN |
| Final | 9/26/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 9/26/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/26/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/26/2023 | Approved | MICHEL ABAJAN |