3420 W LARGA AVE 90039
Certificate Information: 3420 W LARGA AVE 90039
- Application / Permit
- 22014-20000-06237
- Plan Check / Job No.
- B22VN18788
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 12' X 19'-10" TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD NEW ROOF TOP DECK; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Valley
- Current Status
- Issued on 6/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/18/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/20/2023 | STEVEN KIM |
| Building Plans Picked Up | 1/20/2023 | APPLICANT |
| Plan Check Approved | 6/27/2024 | SELLA BENYAMIN |
| Issued | 6/27/2024 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 12/6/2023 | MARIA VENDIVIL |
| Low Impact Development | Cleared | 3/25/2024 | SAMUEL LINN |
| Address approval | Cleared | 3/28/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/8/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/23/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/21/2024 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/23/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/25/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/29/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 4/21/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/21/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Shower Pan | 6/25/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Shower Pan | 7/11/2025 | Approved | REGINA MENDEZ |