3420 W LARGA AVE 90039

Certificate Information: 3420 W LARGA AVE 90039

Application / Permit
22014-20000-06237
Plan Check / Job No.
B22VN18788
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 12' X 19'-10" TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD NEW ROOF TOP DECK; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/27/2024
Issuing Office
Valley
Current Status
Issued on 6/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 SELLA BENYAMIN
Corrections Issued 1/18/2023 SELLA BENYAMIN
Quality Review Completed 1/20/2023 STEVEN KIM
Building Plans Picked Up 1/20/2023 APPLICANT
Plan Check Approved 6/27/2024 SELLA BENYAMIN
Issued 6/27/2024 APPLICANT

Permit Application Clearance Information

Hold Cleared 12/6/2023 MARIA VENDIVIL
Low Impact Development Cleared 3/25/2024 SAMUEL LINN
Address approval Cleared 3/28/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/8/2024 WALLIE JONG
Sewer availability Cleared 4/8/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 5/23/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 8/21/2024 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/27/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/13/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/19/2024 Not Ready for Inspection THOMAS LOGRASSO
Deputy Drilled-In Anchors 9/23/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 11/25/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 1/29/2025 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 4/21/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 4/21/2025 Conditional Approval NICHOLAS LOPEZ
Shower Pan 6/25/2025 Not Ready for Inspection DAVID WILLIAMS
Shower Pan 7/11/2025 Approved REGINA MENDEZ