15525 W TULSA ST 91345

Certificate Information: 15525 W TULSA ST 91345

Application / Permit
22014-20000-06222
Plan Check / Job No.
B22VN18739
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT ( E ) GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/24/2023
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/30/2022 SHANGQIN XIE
Corrections Issued 12/30/2022 SHANGQIN XIE
Applicant returned to address corrections 2/4/2023 SHANGQIN XIE
Plan Check Approved 2/23/2023 SHANGQIN XIE
Issued 2/24/2023 APPLICANT
CofO in Progress 10/18/2023 JENNIFER RABUCHIN
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/6/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 1/6/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/9/2023 MEGAN GODINEZ
Sewer availability Cleared 1/9/2023 MEGAN GODINEZ
Construction near power lines Cleared 2/21/2023 WALTER RAMIREZ
Hold Cleared 5/3/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 5/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/11/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 5/11/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/15/2023 Partial Approval JENNIFER RABUCHIN
Sewer 5/15/2023 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 5/19/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/5/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 7/5/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/5/2023 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/5/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/18/2023 Approved JENNIFER RABUCHIN
Green Building Rough 7/18/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 7/18/2023 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 7/18/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 7/31/2023 Corrections Issued ROBERT GOLD
Interior/Exterior Lathing 7/31/2023 Corrections Issued ROBERT GOLD
Insulation 8/14/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/14/2023 Not Ready for Inspection DAVID ANDERSON
Drywall Nailing 8/21/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/21/2023 Partial Approval JENNIFER RABUCHIN
Shower Pan 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 9/20/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 9/20/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 9/25/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 10/12/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/17/2023 Approved JENNIFER RABUCHIN
Final 10/17/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/17/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 10/17/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/17/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved JENNIFER RABUCHIN