8453 S WADSWORTH AVE 90001

Certificate Information: 8453 S WADSWORTH AVE 90001

Application / Permit
22014-20000-06215
Plan Check / Job No.
B22VN18734
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* ADD 14'-2" X 26'-4" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 3/25/2023
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 SELLA BENYAMIN
Corrections Issued 1/27/2023 SELLA BENYAMIN
Quality Review Completed 2/2/2023 STEVEN KIM
Plan Check Approved 3/10/2023 SELLA BENYAMIN
Issued 3/25/2023 APPLICANT
CofO in Progress 4/8/2026 JOHN QUINTANILLA
CofO Issued 4/9/2026 DEROLD HAUFF
Permit Finaled 4/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/6/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/6/2023 STEVE MELGAR
Roof/Waste drainage to street Cleared 3/6/2023 STEVE MELGAR
Sewer availability Cleared 3/6/2023 STEVE MELGAR
Hold Cleared 6/20/2023 MARIA VENDIVIL

Contact Information

Contractor 129 Builders Inc; Lic. No.: 1051295-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/5/2023 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 4/6/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 4/11/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/15/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 6/28/2023 Approved MICHAEL LEWIS
HVAC-Rough 6/28/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 6/28/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 6/30/2023 Approved MICHAEL LEWIS
Gas Test 8/7/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 8/28/2023 Approved MICHAEL LEWIS
HVAC-Rough 8/28/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 8/28/2023 Approved MICHAEL LEWIS
Underground Mechanical 8/28/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/6/2023 Approved MICHAEL LEWIS
Green Building Rough 9/6/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/17/2023 Approved JOSH MEISTER
Insulation 10/17/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/17/2023 Approved JOSH MEISTER
Final 3/5/2026 No Access for Inspection JOHN QUINTANILLA
Green Building Final 3/5/2026 No Access for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 3/5/2026 No Access for Inspection JOHN QUINTANILLA
Final 3/10/2026 Corrections Issued JOHN QUINTANILLA
Green Building Final 3/10/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 3/10/2026 Approved JOHN QUINTANILLA
Final 4/3/2026 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 4/3/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Approved JOHN QUINTANILLA