2311 W DUANE ST 90039
Certificate Information: 2311 W DUANE ST 90039
- Application / Permit
- 22014-20000-06208
- Plan Check / Job No.
- B22VN18722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 2ND FLOOR 29'-6" x 14'-6" DECK WITH 29'-6" x 1'-11" ADDITION ON 2ND STORY OF 2-STORY SINGLE FAMILY DWELLING TO (N) MASTER BEDROOM AND BATHROOM. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | MADISON ODELL |
| Corrections Issued | 12/24/2022 | MADISON ODELL |
| Building Plans Picked Up | 12/29/2022 | APPLICANT |
| Issued | 2/13/2023 | APPLICANT |
| CofO in Progress | 4/2/2024 | THOMAS LOGRASSO |
| Permit Finaled | 4/11/2024 | DEROLD HAUFF |
| CofO Issued | 4/11/2024 | DEROLD HAUFF |
| Permit Finaled | 4/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/27/2022 | MADISON ODELL |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 1/17/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 1/17/2023 | TREVOR QUAN |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Chaaya,, Danny Camille; Lic. No.: C45555 | P O BOX 46341 LOS ANGELES, CA 90046 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/13/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 5/12/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 6/26/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 6/29/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 7/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/14/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 7/14/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 7/14/2023 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 7/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | THOMAS LOGRASSO |
| MERV13>=Rough | 7/14/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 7/24/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/7/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 8/7/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/7/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/7/2023 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 8/7/2023 | Corrections Issued | THOMAS LOGRASSO |
| Final | 12/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 12/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 12/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/8/2023 | Approved | THOMAS LOGRASSO |
| Final | 3/20/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 3/20/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 3/20/2024 | Approved | THOMAS LOGRASSO |
| Final | 3/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 3/27/2024 | Approved | THOMAS LOGRASSO |
| Final | 4/2/2024 | OK to Issue CofO | THOMAS LOGRASSO |