6546 N WHITMAN AVE 91406

Certificate Information: 6546 N WHITMAN AVE 91406

Application / Permit
22014-20000-06197
Plan Check / Job No.
B22VN18701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
7'-9 1/2" X 8'-10" ADDITION OF LAUNDRY ROOM TO (E) SFD. INTERIOR REMODEL TO CONVERT STEAM ROOM TO BATHROOM, EXISTING RESTROOM CONVERTED TO POWDER ROOM.
Permit Issued
Issued on 2/20/2025
Issuing Office
Valley
Current Status
CofO in Progress on 9/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/21/2022 SERGIO MUNIZ
Corrections Issued 12/21/2022 SERGIO MUNIZ
Applicant returned to address corrections 3/28/2023 RAMA DABADGE
Applicant returned to address corrections 11/1/2024 YAQUB MIRZA
Plan Check Approved 11/7/2024 YAQUB MIRZA
Issued 2/20/2025 APPLICANT
CofO in Progress 9/3/2025 MICKEY YAMASHITA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/5/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/1/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/29/2025 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 5/5/2025 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 5/5/2025 Corrections Issued MICKEY YAMASHITA
Shower Pan 5/5/2025 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 5/14/2025 No Result Entered RUSSELL SCHOONOVER
Footing/Foundation/Slab 5/15/2025 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 6/2/2025 Partial Approval MICKEY YAMASHITA
ELECTRICAL-Rough 6/2/2025 Not Ready for Inspection MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 6/2/2025 Corrections Issued MICKEY YAMASHITA
Green Building Rough 6/2/2025 Not Ready for Inspection MICKEY YAMASHITA
Insulation 6/2/2025 Partial Approval MICKEY YAMASHITA
MERV13>=Rough 6/2/2025 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 6/2/2025 Partial Approval MICKEY YAMASHITA
Drywall Nailing 6/4/2025 Partial Approval MICKEY YAMASHITA
Interior/Exterior Lathing 6/4/2025 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 6/17/2025 Conditional Approval MICKEY YAMASHITA
ELECTRICAL-Rough 6/17/2025 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 6/17/2025 Corrections Issued MICKEY YAMASHITA
Green Building Final 6/17/2025 Corrections Issued MICKEY YAMASHITA
Green Building Rough 6/17/2025 Not Ready for Inspection MICKEY YAMASHITA
MERV13>=Final 6/17/2025 Approved MICKEY YAMASHITA
MERV13>=Rough 6/17/2025 Approved MICKEY YAMASHITA
PLUMBING-Rough 6/17/2025 Corrections Issued MICKEY YAMASHITA
Smoke Detectors 6/17/2025 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 8/7/2025 Conditional Approval MICKEY YAMASHITA
Final 8/7/2025 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 8/7/2025 Conditional Approval MICKEY YAMASHITA
Green Building Final 8/7/2025 Not Ready for Inspection MICKEY YAMASHITA
Green Building Rough 8/7/2025 Not Ready for Inspection MICKEY YAMASHITA
Smoke Detectors 8/7/2025 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 9/2/2025 Approved MICKEY YAMASHITA
ELECTRICAL-Final 9/2/2025 Approved MICKEY YAMASHITA
Final 9/2/2025 OK to Issue CofO MICKEY YAMASHITA
Footing/Foundation/Slab 9/2/2025 Approved MICKEY YAMASHITA
Green Building Final 9/2/2025 Approved MICKEY YAMASHITA
Green Building Rough 9/2/2025 Approved MICKEY YAMASHITA
HVAC-Final 9/2/2025 Approved MICKEY YAMASHITA
PLUMBING-Final 9/2/2025 Approved MICKEY YAMASHITA