22363 W VANOWEN ST 91303

Certificate Information: 22363 W VANOWEN ST 91303

Application / Permit
22014-20000-06193
Plan Check / Job No.
B22VN18695
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 22' X 28'-4" ADDITION TO REAR OF SINGLE FAMILY DWELLING. ALL WORK PER ENG.
Permit Issued
Issued on 5/1/2023
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2023 APPLICANT
Assigned to Plan Check Engineer 1/9/2023 OMAR GARNICA
Corrections Issued 1/10/2023 OMAR GARNICA
Applicant returned to address corrections 3/2/2023 OMAR GARNICA
Applicant returned to address corrections 3/9/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/14/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/28/2023 LUISANGEL VALENZUELA
Plan Check Approved 3/31/2023 LUISANGEL VALENZUELA
Issued 5/1/2023 APPLICANT
CofO in Progress 4/4/2025 GEVORK IPCHYAN
Permit Finaled 5/2/2025 JOHN JANSON
CofO Issued 5/2/2025 JOHN JANSON
Permit Finaled 5/2/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/30/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/28/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 3/7/2023 MARCO SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/4/2023 Conditional Approval TROY SANDERS
PLUMBING-Rough 12/5/2023 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 12/8/2023 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 1/4/2024 Approved HORACE FULTZ
Deputy Reinf. Concrete 1/9/2024 Conditional Approval TROY SANDERS
ELECTRICAL-Rough 2/28/2024 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval GEVORK IPCHYAN
Green Building Rough 3/7/2024 Partial Approval GEVORK IPCHYAN
Deputy Wood Construction 3/11/2024 Conditional Approval TROY SANDERS
BUILDING-Rough-Frame 4/2/2024 Corrections Issued GEVORK IPCHYAN
Green Building Rough 4/2/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 5/31/2024 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval GEVORK IPCHYAN
Interior/Exterior Lathing 7/2/2024 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 7/16/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 7/16/2024 Approved GEVORK IPCHYAN
Green Building Rough 7/16/2024 Approved GEVORK IPCHYAN
HVAC-Rough 7/16/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 7/16/2024 Approved GEVORK IPCHYAN
Underground Mechanical 7/16/2024 Approved GEVORK IPCHYAN
Insulation 7/18/2024 Approved GEVORK IPCHYAN
Drywall Nailing 7/23/2024 Approved GEVORK IPCHYAN
Shower Pan 7/23/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 8/8/2024 Partial Approval GEVORK IPCHYAN
Final 10/3/2024 Corrections Issued GEVORK IPCHYAN
Green Building Final 10/3/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 10/3/2024 Not Ready for Inspection GEVORK IPCHYAN
Final 1/23/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 1/23/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 1/23/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 4/4/2025 Approved GEVORK IPCHYAN
Final 4/4/2025 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 4/4/2025 Approved GEVORK IPCHYAN
HVAC-Final 4/4/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 4/4/2025 Approved GEVORK IPCHYAN