1711 S HOLT AVE 90035

Certificate Information: 1711 S HOLT AVE 90035

Application / Permit
22014-20000-06180
Plan Check / Job No.
B22VN18669
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (324 SQ FT) ADDITION AND MAJOR REMODEL TO (E) 1-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/24/2023
Issuing Office
Valley
Current Status
CofO in Progress on 2/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 RAPHAEL ROSAS
Corrections Issued 1/17/2023 RAPHAEL ROSAS
Quality Review Completed 1/20/2023 STEVEN KIM
Building Plans Picked Up 1/23/2023 APPLICANT
Applicant returned to address corrections 3/13/2023 RAPHAEL ROSAS
Plan Check Approved 4/24/2023 RAPHAEL ROSAS
Issued 4/24/2023 APPLICANT
CofO in Progress 2/26/2024 MEL KHACHATOURIAN
No Progress 2/26/2024 MICHAEL PELHAM
CofO in Progress 2/26/2024 MICHAEL PELHAM

Permit Application Clearance Information

Low Impact Development Cleared 4/17/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 4/18/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 4/18/2023 WALLIE JONG
Sewer availability Cleared 4/18/2023 WALLIE JONG

Contact Information

Contractor Bardi Edmund; Lic. No.: 1037330-B P O BOX 4011      WEST HILLS, CA 91308
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2023 Partial Inspection JEREMY TODD
Deputy Drilled-In Anchors 5/8/2023 Conditional Approval JEREMY TODD
Excavation/Setback/Form/Re-Bar 5/10/2023 Approved JEREMY TODD
Footing/Foundation/Slab 5/10/2023 Approved JEREMY TODD
METHANE-Barrier 5/10/2023 Approved JEREMY TODD
METHANE-Subgrade 5/10/2023 Approved JEREMY TODD
Underground Mechanical 5/10/2023 Approved JEREMY TODD
Deputy Drilled-In Anchors 5/22/2023 Conditional Approval MICHAEL PELHAM
Shower Pan 7/6/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 7/28/2023 Partial Approval ARAM AVEDISIAN
Gas Test 7/28/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 8/9/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 8/23/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 8/23/2023 Approved MEL KHACHATOURIAN
Green Building Rough 8/23/2023 Approved MEL KHACHATOURIAN
HVAC-Rough 8/23/2023 Approved MEL KHACHATOURIAN
METHANE-Rough 8/23/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 8/23/2023 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/1/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/1/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/6/2023 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/11/2023 Approved MEL KHACHATOURIAN
Insulation 9/11/2023 Approved MEL KHACHATOURIAN
Drywall Nailing 9/21/2023 Approved MEL KHACHATOURIAN
Service/Power Release 10/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 12/13/2023 Partial Approval MEL KHACHATOURIAN
Final 12/13/2023 Corrections Issued MEL KHACHATOURIAN
Green Building Final 12/13/2023 Approved MEL KHACHATOURIAN
HVAC-Final 12/13/2023 Approved MEL KHACHATOURIAN
PLUMBING-Final 12/13/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 12/13/2023 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 12/13/2023 Approved MEL KHACHATOURIAN
Final 2/13/2024 OK to Issue CofO MEL KHACHATOURIAN
Service/Power Release 2/13/2024 Approved MEL KHACHATOURIAN
Special/Order Compliance 2/27/2024 Corrections Issued MEL KHACHATOURIAN