3319 1/2-3/4 E ROSEVIEW AVE 90065
Certificate Information: 3319 1/2-3/4 E ROSEVIEW AVE 90065
- Application / Permit
- 22014-20000-06179
- Plan Check / Job No.
- B22VN18668
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE/ WORKSHOP/PATIO TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)and (e) (UNIT #1 3319 1/2-ADU 3319 1/4- UNIT #2319 3/4 )
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | JESSE ARELLANO |
| Corrections Issued | 12/23/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 12/29/2022 | APPLICANT |
| Plan Check Approved | 7/24/2023 | MOHAMMAD ESMAILI |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 7/23/2025 | ALIZAH MAYAGOITIA |
| No Progress | 7/24/2025 | DEROLD HAUFF |
| CofO in Progress | 7/24/2025 | DEROLD HAUFF |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
| CofO Issued | 7/31/2025 | DEROLD HAUFF |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/24/2022 | JESSE ARELLANO |
| Address approval | Cleared | 5/12/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/12/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | STEVE MELGAR |
| Community Plan Implem. Overlay | Cleared | 7/3/2023 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/11/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 12/11/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 12/13/2023 | No Access for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/14/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/14/2024 | Approved | OSVALDO PARAMO |
| Gas Test | 3/27/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 3/27/2024 | Approved | OSVALDO PARAMO |
| Sewer | 3/27/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/10/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/31/2024 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 8/31/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/16/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 9/16/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/2/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 10/25/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/30/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 1/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 3/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 3/12/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/21/2025 | No Access for Inspection | ANTHONY RAMOS |
| Insulation | 4/21/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/23/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/29/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 4/29/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/18/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 7/18/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/22/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |