3319 1/2-3/4 E ROSEVIEW AVE 90065

Certificate Information: 3319 1/2-3/4 E ROSEVIEW AVE 90065

Application / Permit
22014-20000-06179
Plan Check / Job No.
B22VN18668
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO & CONVERT GARAGE/ WORKSHOP/PATIO TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)and (e) (UNIT #1 3319 1/2-ADU 3319 1/4- UNIT #2319 3/4 )
Permit Issued
Issued on 8/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 JESSE ARELLANO
Corrections Issued 12/23/2022 JESSE ARELLANO
Building Plans Picked Up 12/29/2022 APPLICANT
Plan Check Approved 7/24/2023 MOHAMMAD ESMAILI
Issued 8/4/2023 APPLICANT
CofO in Progress 7/23/2025 ALIZAH MAYAGOITIA
No Progress 7/24/2025 DEROLD HAUFF
CofO in Progress 7/24/2025 DEROLD HAUFF
Permit Finaled 7/31/2025 DEROLD HAUFF
CofO Issued 7/31/2025 DEROLD HAUFF
Permit Finaled 7/31/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/24/2022 JESSE ARELLANO
Address approval Cleared 5/12/2023 STEVE MELGAR
Sewer availability Cleared 5/12/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/15/2023 STEVE MELGAR
Community Plan Implem. Overlay Cleared 7/3/2023 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/11/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 12/11/2023 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 12/13/2023 No Access for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 3/14/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 3/14/2024 Approved OSVALDO PARAMO
Gas Test 3/27/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 3/27/2024 Approved OSVALDO PARAMO
Sewer 3/27/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 6/10/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/31/2024 Off-Hour Fees Due
ELECTRICAL-Rough 8/31/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/16/2024 Corrections Issued OSVALDO PARAMO
Green Building Rough 9/16/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/2/2024 Approved OSVALDO PARAMO
Shower Pan 10/25/2024 Approved LILIANA PORTILLO
HVAC-Rough 11/18/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/30/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 1/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 3/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 3/12/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved ALIZAH MAYAGOITIA
Drywall Nailing 4/21/2025 No Access for Inspection ANTHONY RAMOS
Insulation 4/21/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/23/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/29/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 4/29/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 7/7/2025 Approved ALIZAH MAYAGOITIA
Final 7/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 7/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 7/7/2025 Approved ALIZAH MAYAGOITIA
Final 7/18/2025 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 7/18/2025 Approved ALIZAH MAYAGOITIA
Final 7/22/2025 OK to Issue CofO ALIZAH MAYAGOITIA