7745 N VINELAND AVE 91352
Certificate Information: 7745 N VINELAND AVE 91352
- Application / Permit
- 22014-20000-06136
- Plan Check / Job No.
- B22VN18584
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE WITH ADDITION TO (N) 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2022 | DANIEL YIP |
| Corrections Issued | 12/29/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/11/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/16/2024 | AMY GUEVARRA |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 1/28/2026 | MATTHEW NELSON |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/9/2024 | CARLOS AGUILERA |
| Clean Up Green Up | Cleared | 3/11/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/18/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/2/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/2/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/15/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/15/2025 | Approved | MATTHEW NELSON |
| Wood Frame | 4/15/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 4/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Insulation | 4/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 5/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Insulation | 5/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 5/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 5/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 5/16/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/16/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/23/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 6/9/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Final | 9/9/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 9/9/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/9/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 10/1/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 10/1/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 10/1/2025 | Approved | MATTHEW NELSON |
| Final | 10/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 10/6/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Final | 10/10/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/10/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | MATTHEW NELSON |
| Final | 10/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Final | 10/28/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 11/3/2025 | OK to Issue CofO | MATTHEW NELSON |