8136 N ALCOVE AVE 91605

Certificate Information: 8136 N ALCOVE AVE 91605

Application / Permit
22014-20000-06135
Plan Check / Job No.
B22VN18577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) GARAGE CONVERT TO (N) 2-STORY ADU WITH ADDITION PER ORDINANCE LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/13/2023
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 MINA HABILI
Corrections Issued 1/27/2023 MINA HABILI
Applicant returned to address corrections 7/5/2023 MINA HABILI
Plan Check Approved 9/8/2023 MINA HABILI
Issued 9/13/2023 APPLICANT
CofO in Progress 9/10/2025 VINCENT HANLEY
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/23/2023 MATTHEW MAHLEBASHIAN
Roof/Waste drainage to street Cleared 2/23/2023 MATTHEW MAHLEBASHIAN
Eng Process Fee Ord 176,300 Cleared 3/7/2023 MATTHEW MAHLEBASHIAN
Sewer availability Cleared 3/7/2023 MATTHEW MAHLEBASHIAN
Construction near power lines Cleared 6/20/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2023 No Access for Inspection DAVID MATSON
Pre-Inspection 12/5/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 6/28/2024 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/3/2024 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/5/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 7/5/2024 Approved GREGG CUMMINGS
Sewer 7/5/2024 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 7/17/2024 Corrections Issued GREGG CUMMINGS
Green Building Rough 7/17/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/27/2024 Corrections Issued GREGG CUMMINGS
Drywall Nailing 8/27/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 8/27/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval VINCENT HANLEY
Green Building Rough 8/30/2024 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Corrections Issued GREGG CUMMINGS
Drywall Nailing 9/24/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/1/2024 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Partial Approval GREGG CUMMINGS
HVAC-Rough 10/18/2024 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/1/2024 Corrections Issued GREGG CUMMINGS
HVAC-Rough 11/1/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 11/1/2024 Corrections Issued GREGG CUMMINGS
Structural Steel Frame 11/1/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 11/12/2024 Approved GREGG CUMMINGS
Green Building Rough 11/12/2024 Approved GREGG CUMMINGS
HVAC-Rough 11/12/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 11/12/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/19/2024 Approved GREGG CUMMINGS
Insulation 11/25/2024 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 11/25/2024 Partial Approval GREGG CUMMINGS
Drywall Nailing 12/5/2024 Approved MATTHEW NELSON
Shower Pan 12/24/2024 Approved MICHAEL CORTEZ
Grounding or Bonding 12/31/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/6/2025 Approved VINCENT HANLEY
Shower Pan 1/6/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/29/2025 Approved VINCENT HANLEY
Final 7/29/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/29/2025 Approved VINCENT HANLEY
HVAC-Final 7/29/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/29/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 7/29/2025 Approved VINCENT HANLEY
Smoke Detectors 7/29/2025 Approved VINCENT HANLEY
Final 9/9/2025 OK to Issue CofO VINCENT HANLEY