17406 W VALERIO ST 91406

Certificate Information: 17406 W VALERIO ST 91406

Application / Permit
22014-20000-06113
Plan Check / Job No.
B22VN18505
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREGULAR SHAPED 34'-9" X 39'-3" FIRST FLOOR AND (N) 30' X 15'-7" SECOND FLOOR ADDITIION WITH OPEN DECK ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 9/19/2023
Issuing Office
Valley
Current Status
Issued on 9/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/10/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 1/11/2023 OMID HEDAYAT
Building Plans Picked Up 1/20/2023 APPLICANT
Applicant returned to address corrections 8/18/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/18/2023 SEWADA ZADOORAN MILAGARDI
Issued 9/19/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2023 CARLOS AGUILERA
Sewer availability Cleared 4/18/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 5/2/2023 MATTHEW CRAIG
Low Impact Development Cleared 8/2/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 8/2/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/28/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 9/29/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/13/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/3/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 11/22/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 12/19/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 12/19/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 12/19/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 12/19/2023 Corrections Issued RAUL OLAGI
Sewer 12/19/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/3/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/3/2024 Approved RAUL OLAGI
HVAC-Rough 1/3/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 1/3/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 1/3/2024 Approved RAUL OLAGI
Drywall Nailing 1/8/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 1/10/2024 Partial Approval RAUL OLAGI
Drywall Nailing 1/10/2024 Approved RAUL OLAGI
Green Building Rough 1/10/2024 Approved RAUL OLAGI
Insulation 1/10/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 1/10/2024 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 1/24/2024 Approved RAUL OLAGI
Shower Pan 1/24/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/12/2024 Approved RAUL OLAGI
Final 11/12/2024 Corrections Issued RAUL OLAGI
Green Building Final 11/12/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 11/12/2024 Approved RAUL OLAGI