5525 N WILLOW CREST AVE 91601
Certificate Information: 5525 N WILLOW CREST AVE 91601
- Application / Permit
- 22014-20000-06110
- Plan Check / Job No.
- B22VN18499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Garage conversion and 2 story addition for ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- Issued on 6/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2023 | RACHEL BEYENE |
| Corrections Issued | 1/26/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/13/2023 | MICHAEL LANZONE |
| Applicant returned to address corrections | 9/28/2023 | LUKE GONZALES |
| Plan Check Approved | 6/4/2024 | SAMUEL GONZALEZ |
| Issued | 6/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2023 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/18/2023 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 8/29/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/1/2023 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 5/22/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/10/2024 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 12/10/2024 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 12/17/2024 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 12/17/2024 | Approved | JOSE AVILA |
| METHANE-Subgrade | 12/17/2024 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/23/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 12/23/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 1/24/2025 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 7/2/2025 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 7/9/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| METHANE-Rough | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/25/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/19/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/19/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 10/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |