4166 N ELLENITA AVE 91356

Certificate Information: 4166 N ELLENITA AVE 91356

Application / Permit
22014-20000-06102
Plan Check / Job No.
B22VN18488
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 14' X 23' 2-STORY ADDITION AT REAR AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/25/2023
Issuing Office
Metro
Current Status
Issued on 4/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/4/2023 RAPHAEL ROSAS
Corrections Issued 1/6/2023 RAPHAEL ROSAS
Quality Review Completed 1/6/2023 STEVEN KIM
Building Plans Picked Up 1/9/2023 APPLICANT
Applicant returned to address corrections 2/15/2023 RAPHAEL ROSAS
Plan Check Approved 2/27/2023 RAPHAEL ROSAS
Issued 4/25/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/11/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 1/11/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 1/11/2023 ROMAN GUTIERREZ
Sewer availability Cleared 1/11/2023 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 2/27/2023 RAPHAEL ROSAS

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2024 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 7/3/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval JOHN KIDWELL
PLUMBING-Rough 8/13/2024 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 8/15/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 9/4/2024 Conditional Approval JOHN KIDWELL
Green Building Rough 9/4/2024 Not Ready for Inspection JOHN KIDWELL
Rough-Elec/Plmb/HVAC 9/4/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/13/2024 Approved JOHN KIDWELL
Green Building Rough 9/13/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/13/2024 Partial Approval JOHN KIDWELL
Insulation 9/18/2024 Approved JOHN KIDWELL
Shower Pan 9/18/2024 Approved JOHN KIDWELL
Drywall Nailing 9/25/2024 Approved MORRIS JACKSON
Final 11/19/2024 Corrections Issued JOHN KIDWELL
Green Building Final 11/19/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/19/2024 SGSOV Approved JOHN KIDWELL
Smoke Detectors 11/19/2024 Approved JOHN KIDWELL