4323 N TALOFA AVE 91602

Certificate Information: 4323 N TALOFA AVE 91602

Application / Permit
22014-20000-06081
Plan Check / Job No.
B22VN18416
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: 2ND STORY ADU ADDITION TO (E) GARAGE/RECREATION ROOM. ADU PER LAMC 12.22A.33(c) AND (d). INVESTIGATION FEES DUE - Contact Inspector Beaulieu at 818 374-1171 for further info. NOTE: INVESTIGATION FEES ARE A MINIMUM $400.00 OR DOUBLE THE PERMIT FEE WHICHEVER IS GREATER. See LAMC Section 91.107.5.1. Payment of investigation fees due at time of permit issuance. ORDER TO COMPLY ISSUED: 04/12/2017 INSPECTOR: ANTHONY GIANNINI PHONE: 818-374-1171
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 ADRIANA LOPEZ
Corrections Issued 2/15/2023 ADRIANA LOPEZ
Quality Review Completed 2/24/2023 FARUK SEZER
Plan Check Approved 5/6/2023 ADRIANA LOPEZ
Issued 5/8/2023 APPLICANT
CofO in Progress 1/2/2026 JAVIER RAMOS JR
Permit Finaled 1/5/2026 RUBEN SALAS
CofO Issued 1/5/2026 RUBEN SALAS
Permit Finaled 1/5/2026 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 2/28/2023 STEVEN WECHSLER
Address approval Cleared 3/1/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/2/2023 CARLOS AGUILERA
Sewer availability Cleared 3/2/2023 CARLOS AGUILERA

Contact Information

Architect Frutaldo,, Giovanni; Lic. No.: C36430 1525 S SEPULVEDA BLVD   #D    LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Mansuri,, Mehran; Lic. No.: NA78614       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/12/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 2/15/2024 Partial Approval ROBERT GOLD
Footing/Foundation/Slab 3/6/2024 Approved KIRK SANDERS
Deputy Reinf. Concrete 3/11/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/14/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/17/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 6/17/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/9/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/9/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 7/9/2024 Approved CHRISTOPHER ROJAS
Insulation 7/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/9/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/2/2024 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 8/14/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/14/2024 Conditional Approval CHRISTOPHER ROJAS
Drywall Nailing 9/23/2024 Approved CHRISTOPHER ROJAS
Insulation 9/23/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/23/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/28/2024 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 2/27/2025 Partial Inspection CHRISTOPHER ROJAS
Final 2/27/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 2/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 2/27/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 2/27/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 2/27/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 12/16/2025 Approved JAVIER RAMOS JR
Final 12/16/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/16/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 12/16/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 12/16/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/16/2025 Approved JAVIER RAMOS JR
Final 1/2/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 1/2/2026 Approved JAVIER RAMOS JR
HVAC-Final 1/2/2026 Approved JAVIER RAMOS JR