8213 N BELLINGHAM AVE 91605
Certificate Information: 8213 N BELLINGHAM AVE 91605
- Application / Permit
- 22014-20000-06079
- Plan Check / Job No.
- B22VN18410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX 20'X20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 16'X12' ADDITION. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 12/17/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/23/2022 | APPLICANT |
| Plan Check Approved | 1/17/2023 | LUIS RINCON |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 9/8/2023 | DAVID ANDERSON |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 12/27/2022 | RYAN KIM |
| Sewer availability | Cleared | 12/27/2022 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2023 | Conditional Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/8/2023 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 3/24/2023 | Conditional Approval | MATTHEW NELSON |
| Wood Frame | 3/24/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/9/2023 | Corrections Issued | MATTHEW NELSON |
| Gas Test | 5/9/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/9/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/9/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/9/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 5/10/2023 | Approved | MATTHEW NELSON |
| Insulation | 5/17/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/17/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/26/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/26/2023 | Approved | MATTHEW NELSON |
| Final | 8/31/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/31/2023 | Approved | DAVID ANDERSON |
| Green Building Final | 8/31/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 8/31/2023 | Approved | DAVID ANDERSON |
| Final | 9/7/2023 | OK to Issue CofO | DAVID ANDERSON |