19420 W MARILLA ST 91324

Certificate Information: 19420 W MARILLA ST 91324

Application / Permit
22014-20000-06077
Plan Check / Job No.
B22VN18388
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 14'-4"X7'-7"ADDITION TO EXTEND EX BEDROOM W/ NEW BATHROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 HAYATO TSUCHIYA
Corrections Issued 12/17/2022 HAYATO TSUCHIYA
Building Plans Picked Up 12/22/2022 APPLICANT
Applicant returned to address corrections 2/28/2023 JESSE ARELLANO
Applicant returned to address corrections 3/6/2023 JESSE ARELLANO
Plan Check Approved 3/7/2023 SERGIO MUNIZ
Issued 3/7/2023 APPLICANT
CofO in Progress 8/21/2023 JOHN KIDWELL
Permit Finaled 9/1/2023 JOHN JANSON
CofO Issued 9/1/2023 JOHN JANSON
Permit Finaled 9/1/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/21/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 12/22/2022 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/18/2023 Approved DAVID SCANTLIN
Footing/Foundation/Slab 4/18/2023 Approved DAVID SCANTLIN
Wood Frame 4/21/2023 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 5/1/2023 Partial Approval JOHN KIDWELL
Green Building Rough 5/1/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 5/11/2023 Approved JOHN KIDWELL
HVAC-Rough 5/11/2023 Approved JOHN KIDWELL
PLUMBING-Rough 5/11/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/15/2023 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 5/24/2023 Approved DAVID SCANTLIN
Green Building Rough 5/24/2023 Approved DAVID SCANTLIN
Insulation 5/24/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/24/2023 Approved DAVID SCANTLIN
Drywall Nailing 6/2/2023 Approved JOHN KIDWELL
Final 6/21/2023 Corrections Issued JOHN KIDWELL
Green Building Final 6/21/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 6/21/2023 Approved JOHN KIDWELL
Final 8/21/2023 OK to Issue CofO JOHN KIDWELL