14367-14369 W GERMAIN ST 91345
Certificate Information: 14367-14369 W GERMAIN ST 91345
- Application / Permit
- 22014-20000-06063
- Plan Check / Job No.
- B22VN18339
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4'9" X 19'11" ADDITION AND CONVERT (E) 20'2" X 19'11"ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) . ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 12/17/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/19/2022 | APPLICANT |
| Plan Check Approved | 2/16/2023 | MADISON ODELL |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 12/26/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
| CofO Issued | 1/3/2025 | RUBEN SALAS |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/20/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | RYAN KIM |
| Sewer availability | Cleared | 2/15/2023 | RYAN KIM |
| Address approval | Cleared | 2/16/2023 | RYAN KIM |
Contact Information
| Contractor | Grid Line Structures Inc; Lic. No.: 1070999-B | 5304 1/2 LA MIRADA AVE LOS ANGELES, CA 90029 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 3/17/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 3/21/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/21/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/21/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/21/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/5/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 5/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/5/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/19/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 5/25/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/8/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/8/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 6/8/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 6/30/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/30/2023 | Approved | JENNIFER RABUCHIN |
| Sewer | 11/9/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/9/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 6/6/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/6/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/6/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/23/2024 | Approved | JENNIFER RABUCHIN |
| Final | 12/23/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/23/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/23/2024 | Approved | JENNIFER RABUCHIN |